信息系統(tǒng)項目管理師歷年真題英語題翻譯與答案[4]
2012年下半年
●Your company CEO just sent you an E-mail asking you to make a … on your project , which has been in progress for 10 months , to all Identified internal and external stakeholders. He scheduled the presentation for next Monday.You expect more than 50 people to attend. The first step in preparing the presentation is to ( 71 ).
A. define the audience
B. determine the objective
C. decide on the general form of the presentation
D. plan a presentation strategy
信管網(wǎng)參考答案:B
信管網(wǎng)解析:
你負責的項目已經(jīng)進行了10個月,某天,公司的CEO給你發(fā)了一封電子郵件,要你向所有的、確定的、內(nèi)部和外部的干系人報告項目當前的情況,報告的時間定在了下周一,你預計可能會有50多人出席。報告準備的第一步是確定目標。
A:明確報告的聽眾
B:確定目標
C:確定報告的總體格式
D:設計一個報告戰(zhàn)略
●A data warehouse is a subject-oriented data set used for reporting and analusis. Data warehouses can be subdivided into ( 72). Which store subsets of data from a warehouse.
(72) A . OLTPs B. transactions C. data sarts D. OLAPs
信管網(wǎng)參考答案:C
信管網(wǎng)解析:
數(shù)據(jù)倉庫是一個面向主題的用于報告和分析的數(shù)據(jù)集。數(shù)據(jù)倉庫可以細分為數(shù)據(jù)集市,即從一個倉庫中存儲數(shù)據(jù)的子集。
A:聯(lián)機事務處理
B:交易
C:數(shù)據(jù)集市
D:聯(lián)機分析處理
●The communication management plan determines the information and communications needs of the stakeholders. In the following statements related to communication management plan. (73) is false.
A. The communication management plan is contained in or is a subsidiary plan of, the project management plan.
B. The communication management plan can be formal or informal, highly detailed or broadly framed, and based on the needs of the project.
C. The communication manamgement plan organize and summarize the information gathered,and present the results of any analysis as comparedthe performance measurement baseline.
D. The communication management plan can include guidelines project status meetings,project team meetings,e-meetines,and e-mail
信管網(wǎng)參考答案:C
信管網(wǎng)解析:
溝通管理計劃用于確定項目千系人的信息需求和溝通方法,以下關(guān)于溝通管理計劃的敘述中,錯誤的是:溝通管理計劃定期收集、對比和分析基準與實際數(shù)據(jù),以便了解和溝通項目進展與績效情況。
A:溝通管理計劃是項目管理計劃的一部分或子計劃
B:溝通管理計劃可以根據(jù)項目需求是正式或非正式的、非常詳細或高度概括的。
C:溝通管理計劃定期收集、對比和分析基準與實際數(shù)據(jù),以便了解和溝通項目進展與績效情況。
D:溝通管理計劃可包括關(guān)于狀態(tài)會議、項目團隊回憶、網(wǎng)絡會議和電子郵件等的指南。
●Stakeholder management refers to managing communications to satisfy needs of, and resolve issues with,project stakeholders. The (74) is useful responsible for stakeholder management.
(74) A. PMO B. CIO C. CCB D. PM
信管網(wǎng)參考答案:D
信管網(wǎng)解析:
項目干系人管理是指為滿足干系人的需要而與之溝通,并解決所發(fā)生的問題,通常,項目經(jīng)理(PM)負責項目干系人管理。
A:項目管理辦公室
B:首席信息官
C:變更控制委員會。
D:項目經(jīng)理
●The most crucial time for project risk assessment is (75).
A. when a problem surfaces
B. during the planning phase
C. during the close-out phase
D. after the project schedule has been published
信管網(wǎng)參考答案:B
信管網(wǎng)解析:
進行項目風險評估最關(guān)鍵的時候是:規(guī)劃階段
A:問題出現(xiàn)時
B:規(guī)劃階段
C:結(jié)束階段
D:項目進度公布后
2012上半年
71. The connection between two networks tofrom an internet is handled by a machine known as a __.
A、bridge B、server C、router D、switch
信管網(wǎng)參考答案:C
信管網(wǎng)試題解析:
在互聯(lián)網(wǎng)中將兩個網(wǎng)絡連接在一起的設備被稱為路由器
72. The TCP protocol is a __ layer protocol.
A、physical B、network C、transport D、application
信管網(wǎng)參考答案:C
信管網(wǎng)試題解析:
TCP協(xié)議是傳輸層協(xié)議。
73. An example of scope verification is __.
A、review the performance ofan installed software module
B、managing changes to the projectschedule
C、decomposing the WBS to a workpackage level
D、performing a benefit/cost analysis to determineif we shuould proceed with the project
信管網(wǎng)參考答案:A
信管網(wǎng)試題解析:
范圍驗證的一個示例是__。
A.查看己安裝的軟件模塊的性能
B.項目進度變更管理
C.分解到工作包級別WBS
D.執(zhí)行成本/效益分析,以確定是否我們應該繼續(xù)進行項目
范圍驗證,這一過程用于正式驗收項目的階段成果或項目的最終成果,也叫范圍確認。驗收的作用就是檢查系統(tǒng)或軟件是否能正常運行,所以選擇A
74. Your project is behind schedule due toconflict between team members . Having resolved the conflict,to get the projectback on schedule , you should consider __.
A、crashing the schedule
B、performing resource leveling
C、conducting reverse resourceallocation scheduling
D、utilizing the critical chairresources
信管網(wǎng)參考答案:B
信管網(wǎng)試題解析:
由于團隊成員之間的沖突,造成了項目進度落后于計劃,為了解決沖突以使得項目如期完成,你應該考慮:A.重新安排時間表 B.執(zhí)行資源調(diào)配 C.進行反向資源分配調(diào)度 D.利用關(guān)鍵的主要資源
75. You have just taken control of aproject in the middle of execution and need to learn who has approval authorityfor revisions in scope . __ document provides this information.
A、Resource assignment matrix B、Change control plan
C、Project charter D、Client organization chart
信管網(wǎng)參考答案:B
信管網(wǎng)試題解析:
在項目執(zhí)行的過程中你剛剛獲得項目的控制權(quán)力,并且需要了解誰具有范圍修正的權(quán)限,__文件提供了該信息? A.資源分配矩陣B.變更控制計劃 C.項目章程 D.客戶的組織結(jié)構(gòu)圖
掃碼關(guān)注公眾號
溫馨提示:因考試政策、內(nèi)容不斷變化與調(diào)整,信管網(wǎng)網(wǎng)站提供的以上信息僅供參考,如有異議,請以權(quán)威部門公布的內(nèi)容為準!
信管網(wǎng)致力于為廣大信管從業(yè)人員、愛好者、大學生提供專業(yè)、高質(zhì)量的課程和服務,解決其考試證書、技能提升和就業(yè)的需求。
信管網(wǎng)軟考課程由信管網(wǎng)依托10年專業(yè)軟考教研傾力打造,官方教材參編作者和資深講師坐鎮(zhèn),通過深研歷年考試出題規(guī)律與考試大綱,深挖核心知識與高頻考點,為學員考試保駕護航。面授、直播&錄播,多種班型靈活學習,滿足不同學員考證需求,降低課程學習難度,使學習效果事半功倍。
相關(guān)內(nèi)容