第
24題: 某項(xiàng)目經(jīng)理在估算某軟件開發(fā)活動(dòng)的成本時(shí),發(fā)現(xiàn)該項(xiàng)目模塊與歷史項(xiàng)目高度相似,但當(dāng)前項(xiàng)目要求引入AT技術(shù),導(dǎo)致分開發(fā)工作量增加10%。項(xiàng)目經(jīng)理參考了歷史項(xiàng)目的功能點(diǎn)成本數(shù)據(jù),并結(jié)合AI技術(shù)的復(fù)雜度系數(shù)進(jìn)行調(diào)整,最終得出活動(dòng)成本估算值。項(xiàng)目經(jīng)理主要使用了以下哪種技術(shù)()。
A.三點(diǎn)估算
B.類比估算
C.參數(shù)估算
D.儲(chǔ)備分析答案解析與討論:
www.jazzmuze.com/st/7821828834.html第
25題: 監(jiān)督溝通過程的輸入不包含()。
A.已開展的溝通的信息
B.計(jì)劃溝通的實(shí)際開展情況
C.關(guān)于已開展的溝通類型和數(shù)量的數(shù)據(jù)
D.項(xiàng)目早期的經(jīng)驗(yàn)教訓(xùn)答案解析與討論:
www.jazzmuze.com/st/7821928834.html第
26題: () is the process of developing options, selecting strategies, and agreeing on actions to address overall project risk exposure, as well as to treat individual project risks.
A. Plan risk responses
B. Plan risk management
C. Implement risk responses
D. Perform quantitative risk analysis答案解析與討論:
www.jazzmuze.com/st/7822028834.html第
53題: When using earned value analysis, the( )is compared to actual results to determine if a change, corrective action, or preventive action is necessary.
A. cost baseline
B. performance measurement baseline
C. schedule baseline
D. scope baseline
答案解析與討論:
www.jazzmuze.com/st/782349290.html第
54題: 監(jiān)督是貫穿于整個(gè)項(xiàng)目的項(xiàng)目管理活動(dòng)之一,包括收集、測(cè)量和( ),以及預(yù)測(cè)趨勢(shì),以便推動(dòng)( )。
A 分析收集數(shù)據(jù) 數(shù)據(jù)分析
B.分析測(cè)量結(jié)果 過程改進(jìn)
C.評(píng)估項(xiàng)目績(jī)效 績(jī)效優(yōu)化
D.檢查項(xiàng)目風(fēng)險(xiǎn) 風(fēng)險(xiǎn)管理
答案解析與討論:
www.jazzmuze.com/st/782355046.html第
55題: 某醫(yī)療器械公司正在研發(fā)一款新型的醫(yī)療診斷設(shè)備,該設(shè)備需要符合嚴(yán)格的國(guó)家和國(guó)際醫(yī)療設(shè)備標(biāo)準(zhǔn)。但相關(guān)法規(guī)和標(biāo)準(zhǔn)不斷更新,如果等產(chǎn)品開發(fā)完成后再進(jìn)行合規(guī)性測(cè)試,可能會(huì)導(dǎo)致產(chǎn)品不符合最新的法規(guī)要求,無(wú)法通過干系人的驗(yàn)收,該項(xiàng)目適合采用( )的開發(fā)方法,項(xiàng)目經(jīng)理需要具有( )領(lǐng)導(dǎo)風(fēng)格。
A. 適應(yīng)型 服務(wù)型
B. 適應(yīng)型 指導(dǎo)型
C. 預(yù)測(cè)型 變革型
D. 預(yù)測(cè)型 權(quán)威型
答案解析與討論:
www.jazzmuze.com/st/782365819.html