中文字幕综合一区,伊人av网,欧美中日韩在线,亚洲国产香蕉视频,黄视频在线免费,天天操天天爱天天爽,狠狠躁天天躁

軟題庫 移動APP 掃碼下載APP 隨時隨地移動學(xué)習(xí) 培訓(xùn)課程
試卷名稱 信息系統(tǒng)項目管理師-pmp練習(xí)題-1
考試中心《信息系統(tǒng)項目管理師-pmp練習(xí)題-1》在線考試
試卷年份2017年下半年
試題題型【單選題】
試題內(nèi)容

At a project status team meeting, one team member disagrees with another team member regarding a corrective action. The debate escalates and they are soon both adamantly, Other team members are not participating. The project manager directs the team on the corrective action to use.  What conflict resolution technique did the project manager use ?
A、Compromising
B、Forcing
C、Withdrawing
D、Smoothing


相關(guān)試題

推薦文章
合作網(wǎng)站內(nèi)容