信息系統(tǒng)項(xiàng)目管理師每日一練試題內(nèi)容(2018/10/15)
試題1: 在總監(jiān)理工程師臨時(shí)不在工作崗位時(shí),總監(jiān)理工程師可以委托總監(jiān)理工程師代表完成( )。
A. 簽發(fā)工程竣工監(jiān)理報(bào)告
B. 處理索賠、審批工程延期
C. 調(diào)換不稱職的監(jiān)理人員
D. 組織編制并簽發(fā)監(jiān)理日志
( )不屬于網(wǎng)絡(luò)接入技術(shù)
A.HFC
B.xDSL
C.NetBEUI
D.DDN
以下敘述正確的是( )
A.ERP軟件強(qiáng)調(diào)事后核算,而財(cái)務(wù)軟件強(qiáng)調(diào)及時(shí)調(diào)整
B.財(cái)務(wù)軟件強(qiáng)調(diào)事后核算,而ERP軟件強(qiáng)調(diào)事前計(jì)劃和及時(shí)調(diào)整
C.ERP軟件強(qiáng)調(diào)事后核算,而進(jìn)銷存軟件比較關(guān)心每種產(chǎn)品的成本構(gòu)成
D.進(jìn)銷存軟件強(qiáng)調(diào)事后核算,而財(cái)務(wù)軟件強(qiáng)調(diào)及時(shí)調(diào)整
某公司希望舉辦一個(gè)展銷會(huì)以擴(kuò)大市場(chǎng),選擇北京、天津、上海、深圳作為候選會(huì)址。獲利情況除了會(huì)址關(guān)系外,還與天氣有關(guān)。天氣可分為晴、多云、多雨三種。通過天氣預(yù)報(bào),估計(jì)三種天氣情況可能發(fā)生的概率為0.25、0.50、0.25,其收益(單位:人民幣萬元)情況見下表。使用決策樹進(jìn)行決策的結(jié)果為( )。
A.北京
B.天津
C.上海
D.深圳
甲乙丙為三個(gè)獨(dú)立項(xiàng)目,NPV 甲=12 萬元,NPV 乙=15 萬元,NPV 丙=18 萬元,三個(gè)項(xiàng)目的初始投資額相同,并且回收期相同,則應(yīng)優(yōu)先選擇( )項(xiàng)目進(jìn)行投資。
A.甲
B.乙
C.丙
D.甲或乙
數(shù)據(jù)安全的目的是實(shí)現(xiàn)數(shù)據(jù)的( )。
A、唯一性、不可替代性、機(jī)密性
B、機(jī)密性、完整性、不可否認(rèn)性
C、完整性、確定性、約束性
D、不可否認(rèn)性、備份、效率
掙值管理是一種綜合了范圍、時(shí)間、成本績(jī)效測(cè)量的方法,通過與計(jì)劃完成的工作量、實(shí)際掙得的收益、實(shí)際的成本進(jìn)行比較,可以確定成本進(jìn)度是否按計(jì)劃執(zhí)行。下圖中標(biāo)號(hào)所標(biāo)示的區(qū)間依次應(yīng)填寫( )。
A、①進(jìn)度落后 ②成本差CV ③進(jìn)度差SV
B、①成本差CV ②進(jìn)度差SV ③進(jìn)度落后時(shí)間
C、①進(jìn)度差SV ②成本差CV ③進(jìn)度落后時(shí)間
D、①進(jìn)度落后 ②進(jìn)度差SV ③成本差CV
某項(xiàng)目有五個(gè)獨(dú)立的子項(xiàng)目,小張和小李各自獨(dú)立完成項(xiàng)目所需的時(shí)間如下表所示:
則如下四種安排中( )的工期最短。
A.小張做甲和乙,小李做丙、丁和戊
B.小張做乙,小李做甲、丙、丁和戊
C.小張做乙、丁和戊,小李做甲和丙
D.小張做甲、乙和丁,小李做丙和戊
The communication management plan determines the information and communications needs of the stakeholders. In the following statements related to communication management plan. ( ) is false.
A. The communication management plan is contained in or is a subsidiary plan of, the project management plan.
B. The communication management plan can be formal or informal, highly detailed or broadly framed, and based on the needs of the project.
C. The communication manamgement plan organize and summarize the information gathered,and present the results of any analysis as comparedthe performance measurement baseline.
D. The communication management plan can include guidelines project status meetings,project team meetings,e-meetines,and e-mail
軟件需求包括功能需求、非功能需求、設(shè)計(jì)約束三個(gè)主要部分,其中()屬于功能需求內(nèi)容。
A、軟件的可靠性
B、軟件運(yùn)行的環(huán)境
C、軟件需要完成哪些事情
D、軟件的開發(fā)工具
溫馨提示:因考試政策、內(nèi)容不斷變化與調(diào)整,信管網(wǎng)網(wǎng)站提供的以上信息僅供參考,如有異議,請(qǐng)以權(quán)威部門公布的內(nèi)容為準(zhǔn)!
信管網(wǎng)致力于為廣大信管從業(yè)人員、愛好者、大學(xué)生提供專業(yè)、高質(zhì)量的課程和服務(wù),解決其考試證書、技能提升和就業(yè)的需求。
信管網(wǎng)軟考課程由信管網(wǎng)依托10年專業(yè)軟考教研傾力打造,官方教材參編作者和資深講師坐鎮(zhèn),通過深研歷年考試出題規(guī)律與考試大綱,深挖核心知識(shí)與高頻考點(diǎn),為學(xué)員考試保駕護(hù)航。面授、直播&錄播,多種班型靈活學(xué)習(xí),滿足不同學(xué)員考證需求,降低課程學(xué)習(xí)難度,使學(xué)習(xí)效果事半功倍。
發(fā)表評(píng)論 查看完整評(píng)論 | |