The project manager conducts an interview with a key stakeholder. This stakeholder insists that the project be completed by a certain date to allow the resulting product to be arranged manufacture in time for a critical trade exhibition. The stakeholder also insists that the product must pass existing international safety standards. The stakeholder will not release the initial fund for the project kick-off unless both conditions are included. Where must the project manager include these conditions?
A、Project summary milestones
B、 Project contract summary
C、 Project high-level requirements
D、 Project exit criteria