Based on project progress made to date, a project team wants to change the risk management approach they chose at the beginning of the project. The project manager approves this request to ensure project success, and project activities continue.What should the project manager have done instead?
根據(jù)迄今為止取得的項目進展,項目團隊希望改變他們在項目開始時選擇的風(fēng)險管理方法。為了確保項目成功,項目活動繼續(xù)進行,項目經(jīng)理批準(zhǔn)了這一請求。項目經(jīng)理本應(yīng)該怎么做?
?A.Referred to the risk management plan, and encouraged the project team to follow the project’s agreed-upon change control process.查閱風(fēng)險管理計劃,并鼓勵項目團隊遵循項目的約定變更控制流程
?B.Refuse to make the changes, as the approach was already agreed-upon by the stakeholders拒絕進行變更,因為這種方法已經(jīng)獲得相關(guān)方的同意
?C.Told the project team that the risk management approach was determined based on the needs of the project and cannot be changed.告訴項目團隊,風(fēng)險管理方法是根據(jù)項目需求確定的,不能改變
?D.Rewarded the project team for identifying a new risk management approach.因項目團隊確定新的風(fēng)險管理方法而獎勵團隊