中文字幕综合一区,伊人av网,欧美中日韩在线,亚洲国产香蕉视频,黄视频在线免费,天天操天天爱天天爽,狠狠躁天天躁

軟題庫 移動APP 掃碼下載APP 隨時隨地移動學習 培訓課程
試卷名稱 考前沖刺預測卷二(綜合知識)
考試中心《考前沖刺預測卷二(綜合知識)》在線考試
試卷年份2013年上半年
試題題型【單選題】
試題內(nèi)容

During the risk analysis process. it is determined that one identified risk event cannot be avoided, mitigated, or insured. This risk event is a critical item that could cause the project to fail if it occurs. The best option for the project manager is to:  ( )
A. Continue to search for an insurance company that would assume the risk
B. Place special emphasis on the risk event to intensely manage that item and all interfacing items
C. Play down the risk and the team will find a means of overcoming any failure
D. Ignore the risk assessment because any assigned value is a point estimate which is never precisely the expected state of nature


相關試題

推薦文章
合作網(wǎng)站內(nèi)容