Project A is being administered using a matrix form of organization. The project manager reports to a senior vice president who provides visible support to the project. In this scenario, which of the following statements best describes the relative power of the project manager?
A、The project manager will probably not be challenged by project stakeholders
B、In this strong matrix, the balance of power is shifted to the functional line managers
C、In this tight matrix, the balance of power is shifted to the project manager.
D、In this tight matrix, the balance of power is shifted to the project manager.