The development of a new software application had been completed on time and within budget although resources were new to the technology. During the code install, it was determined that certain aspects of the hardware needed to be configured before the new application could be utilized. The customer was incredibly upset and disappointed as this would cause a delay in the implementation. What could have been the cause for this situation?
A、The customer did not request the hardware to be appropriately set up.
B、The hardware configuration was too expensive and would have caused the project to run over budget.
C、A work breakdown structure was not created adequately.
D、The resources completed a three-week training course versus a more through six-week training course.
10年專(zhuān)注信管,信管教育專(zhuān)注者,信管網(wǎng)優(yōu)勢(shì)
免費(fèi)試聽(tīng)信管網(wǎng)信息系統(tǒng)項(xiàng)目管理師課程
全國(guó)前50名高分學(xué)員訪談:董麗(174)、李思...
信息系統(tǒng)項(xiàng)目管理師高端班培訓(xùn)課程
信管老師100小時(shí)直播課程
軟考報(bào)名專(zhuān)題(報(bào)名時(shí)間、入口等)
中級(jí)系統(tǒng)集成項(xiàng)目管理工程師通關(guān)課程
系統(tǒng)規(guī)劃與管理師課程(考試介紹與題型分析)
軟題庫(kù):軟考在線題庫(kù)、支持手機(jī)答題