中文字幕综合一区,伊人av网,欧美中日韩在线,亚洲国产香蕉视频,黄视频在线免费,天天操天天爱天天爽,狠狠躁天天躁

軟題庫 移動APP 掃碼下載APP 隨時隨地移動學習 培訓課程
試卷名稱 2017年信息系統(tǒng)項目管理師最新英語模擬題(3)
考試中心《2017年信息系統(tǒng)項目管理師最新英語模擬題(3)》在線考試
試卷年份2017年下半年
試題題型【單選題】
試題內(nèi)容

The engineering department wants the project objective to be a lo percent improvement in throughput. The information technology department wants no more than five percent of its resources to be used on the project. Management, who is also your boss, wants the project team to decrease tax liability. The BEST thing you can do is:
A、put a plan together that meets all the objectives.
B、have these people get together and agree on one objective.
C、include the engineering and information technology objectives but hold further meetings regarding management's objective.
D、include only management's objective.


相關(guān)試題

推薦文章
合作網(wǎng)站內(nèi)容