A consultant company has been awarded a contract to expand an existing facility in a recently populated area. The executives select a project manager and inform them their commitment to support the project and the sensitive nature of the issues. What should be considered firstly by the project manager?
A、develop the project charter and confirm this project formally
B、negotiate about the assignment of internal communication experts
C、execute an roughly analysis of stakeholders
D、define the expectations, objects and success criteria in the statement of works