項(xiàng)目X已完成60%,落后于進(jìn)度且超出預(yù)算。由于其他更高優(yōu)先級的項(xiàng)目,項(xiàng)目發(fā)起人已經(jīng)撤出資金,而且部門經(jīng)理已經(jīng)將所有團(tuán)隊(duì)成員分配給項(xiàng)目Y.項(xiàng)目經(jīng)理應(yīng)該怎么做?
A、修訂項(xiàng)目管理計(jì)劃,把變化反映在范圍中
B、為項(xiàng)目Y召開一次會議
C、記錄并存檔項(xiàng)目X的經(jīng)驗(yàn)教訓(xùn)
D、為項(xiàng)目X計(jì)算EAC和ETC