項(xiàng)目經(jīng)理最近被指派到一個(gè)正在進(jìn)行的軟件開發(fā)項(xiàng)目。利害關(guān)系者根據(jù)前一項(xiàng)目經(jīng)理的報(bào)告,認(rèn)為項(xiàng)目符合進(jìn)度與預(yù)算安排。新項(xiàng)目經(jīng)理在閱讀相關(guān)項(xiàng)目文件后,了解到項(xiàng)目進(jìn)度滯后并且超出預(yù)算。項(xiàng)目經(jīng)理應(yīng)該怎么做?
A、努力快速跟進(jìn)項(xiàng)目以滿足進(jìn)度需求
B、向利害關(guān)系者報(bào)告評(píng)估情況
C、利用現(xiàn)有資源繼續(xù)運(yùn)行項(xiàng)目
D、與干系人開會(huì)并申請(qǐng)更多資源