中文字幕综合一区,伊人av网,欧美中日韩在线,亚洲国产香蕉视频,黄视频在线免费,天天操天天爱天天爽,狠狠躁天天躁

軟題庫(kù) 移動(dòng)APP 掃碼下載APP 隨時(shí)隨地移動(dòng)學(xué)習(xí) 培訓(xùn)課程
試卷名稱 信息系統(tǒng)項(xiàng)目管理師-pmp練習(xí)題-3
考試中心《信息系統(tǒng)項(xiàng)目管理師-pmp練習(xí)題-3》在線考試
試卷年份2017年下半年
試題題型【單選題】
試題內(nèi)容

A six-month project is in the third month and is 20% complete. The project’s budget is US$ 3 million and the current spending is US$ 1.8 million. The project manager reports to the sponsor about the project status. The current cost of the project performance index (CPI), and schedule performance index (SPI) is:
A、CPI = 0.33 and SPI = 0.40
B、CPI = 0.60 and SPI = 0.50
C、CPI = 1.20 and SPI = 2.00
D、CPI = 3.00 and SPI = 2.50


相關(guān)試題

推薦文章