中文字幕综合一区,伊人av网,欧美中日韩在线,亚洲国产香蕉视频,黄视频在线免费,天天操天天爱天天爽,狠狠躁天天躁

軟題庫 移動(dòng)APP 掃碼下載APP 隨時(shí)隨地移動(dòng)學(xué)習(xí) 培訓(xùn)課程
試卷名稱 信息系統(tǒng)項(xiàng)目管理師-pmp練習(xí)題-2
考試中心《信息系統(tǒng)項(xiàng)目管理師-pmp練習(xí)題-2》在線考試
試卷年份2017年下半年
試題題型【單選題】
試題內(nèi)容

The member monitoring the processes looks at the product’s control chart. There are six consecutive points below the mean, but within control limits. The project manager should take which of the following actions?
A、Adjust the process.
B、Create an Ishikawa diagram.
C、Conduct a Design of Experiments.
D、No action is required.


相關(guān)試題

推薦文章
合作網(wǎng)站內(nèi)容