中文字幕综合一区,伊人av网,欧美中日韩在线,亚洲国产香蕉视频,黄视频在线免费,天天操天天爱天天爽,狠狠躁天天躁

軟題庫 移動APP 掃碼下載APP 隨時(shí)隨地移動學(xué)習(xí) 培訓(xùn)課程
試卷名稱 信息系統(tǒng)項(xiàng)目管理師-pmp練習(xí)題-1
考試中心《信息系統(tǒng)項(xiàng)目管理師-pmp練習(xí)題-1》在線考試
試卷年份2017年下半年
試題題型【單選題】
試題內(nèi)容

A project consists of three major activities: A. Euro conversion development (5weeks); B. General Ledger development (6 weeks); C. CRM implementation (7weeks). Activity B cannot start until activity A is completed and an additional week is spent on resource reassignment. Activity C can only start a week after activity B has started. What is the earliest duration for the project completion?


A、12 weeks
B、13 weeks
C、14 weeks
D、18 weeks


相關(guān)試題

推薦文章
合作網(wǎng)站內(nèi)容