中文字幕综合一区,伊人av网,欧美中日韩在线,亚洲国产香蕉视频,黄视频在线免费,天天操天天爱天天爽,狠狠躁天天躁

軟題庫 移動(dòng)APP 掃碼下載APP 隨時(shí)隨地移動(dòng)學(xué)習(xí) 培訓(xùn)課程
試卷名稱 信息系統(tǒng)項(xiàng)目管理師-pmp練習(xí)題-1
考試中心《信息系統(tǒng)項(xiàng)目管理師-pmp練習(xí)題-1》在線考試
試卷年份2017年下半年
試題題型【單選題】
試題內(nèi)容

Project manager according to the agreed project scope required the ability to determine the project team member candidates. What should the project manager do?
A、Negotiate with the functional manager to distribute the resource of project.
B、 Negotiate with the identified resources to join the project.
C、 Escalate the resource needs to the project sponsor immediately.
D、 Update the risk management log with the need for company.


相關(guān)試題