An IS auditor has been asked to participate in project initiation meetings for a critical project. The IS auditor's MAIN concern should be that the:
A、complexity and risks associated with the project have been analyzed.
B、resources needed throughout the project have been determined.
C、project deliverables have been identified.
D、a contract for external parties involved in the project has been completed.
10年專(zhuān)注信管,信管教育專(zhuān)注者,信管網(wǎng)優(yōu)勢(shì)
免費(fèi)試聽(tīng)信管網(wǎng)信息系統(tǒng)項(xiàng)目管理師課程
全國(guó)前50名高分學(xué)員訪(fǎng)談:董麗(174)、李思...
信息系統(tǒng)項(xiàng)目管理師高端班培訓(xùn)課程
信管老師100小時(shí)直播課程
軟考報(bào)名專(zhuān)題(報(bào)名時(shí)間、入口等)
中級(jí)系統(tǒng)集成項(xiàng)目管理工程師通關(guān)課程
系統(tǒng)規(guī)劃與管理師課程(考試介紹與題型分析)
軟題庫(kù):軟考在線(xiàn)題庫(kù)、支持手機(jī)答題