When identifying an earlier project completion time, which is to be obtained by paying a premium for early completion, the activities that should be selected are those:
A、whose sum of activity time is the shortest.
B、that have zero slack time.
C、that give the longest possible completion time.
D、whose sum of slack time is the shortest.