1、 Managing risk and documenting them is very important in project planning process. You are in the process of defining key risks, including constraints and assumptions, and planned responses and contingencies. These details will be included in the( )
A. project management plan
B. project baseline
C. risk response plan
D. risk baseline
信管網(wǎng)參考答案:A
在項目計劃過程中,風(fēng)險管理和記錄是非常重要的。您正在定義關(guān)鍵風(fēng)險,包括約束和假設(shè),以及計劃的響應(yīng)和意外事件。這些詳細信息將包含在()
A、 項目管理計劃
B、 項目基線
C、 風(fēng)險應(yīng)對計劃
D、 風(fēng)險基線
查看解析:http://www.jazzmuze.com/st/2879.html
2、 The project budget has been finalized.Additional work has been discovered that was not planned for in the budget or project scope. ( )could provide the fund to cover the newly discovered work item.
A. Contingency reserve
B. Project profit
C. Management reserve
D. Special fund
信管網(wǎng)參考答案:C
項目預(yù)算已經(jīng)定稿。附加發(fā)現(xiàn)預(yù)算或項目范圍內(nèi)沒有計劃的工作。()可以為新發(fā)現(xiàn)的工作項目提供資金。
A、 應(yīng)急準(zhǔn)備金
B、 項目利潤
C、 管理準(zhǔn)備金
D、 專項基金
溫馨提示:因考試政策、內(nèi)容不斷變化與調(diào)整,信管網(wǎng)網(wǎng)站提供的以上信息僅供參考,如有異議,請以權(quán)威部門公布的內(nèi)容為準(zhǔn)!
信管網(wǎng)致力于為廣大信管從業(yè)人員、愛好者、大學(xué)生提供專業(yè)、高質(zhì)量的課程和服務(wù),解決其考試證書、技能提升和就業(yè)的需求。
信管網(wǎng)軟考課程由信管網(wǎng)依托10年專業(yè)軟考教研傾力打造,官方教材參編作者和資深講師坐鎮(zhèn),通過深研歷年考試出題規(guī)律與考試大綱,深挖核心知識與高頻考點,為學(xué)員考試保駕護航。面授、直播&錄播,多種班型靈活學(xué)習(xí),滿足不同學(xué)員考證需求,降低課程學(xué)習(xí)難度,使學(xué)習(xí)效果事半功倍。
發(fā)表評論 查看完整評論 | |