信息系統(tǒng)項(xiàng)目管理師每日一練試題內(nèi)容(2017/5/1)
試題1: 項(xiàng)目管理中,保證客戶和干系人滿意的最重要的活動(dòng)是( )。
A. 績(jī)效測(cè)評(píng)存檔
B. 變更匯報(bào)和項(xiàng)目計(jì)劃更新以及其他適當(dāng)?shù)捻?xiàng)目文件
C. 及時(shí)且有規(guī)律地匯報(bào)項(xiàng)目績(jī)效
D. 將需求記錄下來(lái)整理為文件
Many of the activities performed during the preliminary investigation are still being conducted in(1 ), but in much greater depth than before. During this phase, the analyst must become fully aware of the(2 ) and must develop enough knowledge about the(3 ) and the existing systems to enable an effective solution to be proposed and implemented. Besides the(4 ) for process and data of current system, the deliverable from this phase also includes the(5 ) for the proposed system.
(1)A. analysis phase
B. design phase
C. implementation phase
D. maintenance phase
(2)A. main symptom
B. root problem
C. final blueprint
D. data specification
(3)A. hardware environment
B. testing environment
C. software environment
D. business environment
(4)A. logical models
B. physical models
C. design models
D. implementation models
(5)A. hardware and software specification
B. system performance specification
C. formal requirements definition
D. general problem statement
某電信企業(yè)要建設(shè)一個(gè)CRM系統(tǒng)(包括呼叫中心和客服中心),系統(tǒng)集成一級(jí)資質(zhì)企業(yè)甲和系統(tǒng)集成二級(jí)資質(zhì)企業(yè)乙參與該系統(tǒng)建設(shè)。關(guān)于合同的簽訂,下面說(shuō)法中,( )是正確的。
A.如電信企業(yè)和乙簽訂CRM建設(shè)總包臺(tái)同,則乙和甲就呼叫中心的建設(shè)只能簽訂分包合同
B.如電信企業(yè)和乙簽訂客服中心建設(shè)總包臺(tái)同,則電信企業(yè)和甲就CRM的建設(shè)只能簽訂總價(jià)合同
C.如電信企業(yè)和乙簽訂客服中心建設(shè)單項(xiàng)承包合同,則電信企業(yè)和甲就CRM的建設(shè)只能簽訂單項(xiàng)承包合同
D.如電信企業(yè)和甲簽訂CRM建設(shè)總價(jià)合同,則甲和乙就呼叫中心的建設(shè)只能簽訂單價(jià)合同
以下不屬于項(xiàng)目可行性研究?jī)?nèi)容是( )。
A.項(xiàng)目的詳細(xì)管理計(jì)劃
B.項(xiàng)目的風(fēng)險(xiǎn)因素及其對(duì)策
C.項(xiàng)目的社會(huì)影響性分析
D.項(xiàng)目的財(cái)務(wù)盈利能力評(píng)價(jià)
下列( )做法不屬于進(jìn)度壓縮。
A. 某項(xiàng)目經(jīng)理發(fā)現(xiàn)項(xiàng)目工期延后,于是開(kāi)始讓項(xiàng)目組成員開(kāi)始加班加點(diǎn),提高加班工資,以期待能在規(guī)定時(shí)間內(nèi)完成項(xiàng)目
B. 某項(xiàng)目經(jīng)理發(fā)現(xiàn)項(xiàng)目組成員由于對(duì)技術(shù)的掌握不熟練,造成進(jìn)展緩慢,延誤工期,于是指派了有經(jīng)驗(yàn)的人員幫助完成
C. 為了節(jié)省時(shí)間,在需求設(shè)計(jì)還沒(méi)有完成時(shí),項(xiàng)目經(jīng)理就通知組內(nèi)編程人員開(kāi)始編寫(xiě)代碼
D. 項(xiàng)目經(jīng)理啟用應(yīng)急時(shí)間來(lái)增加一些項(xiàng)目時(shí)間
UML中的用例和用例圖的主要用途是描述系統(tǒng)的( )。
A.功能需求
B.詳細(xì)設(shè)計(jì)
C.體系結(jié)構(gòu)
D.內(nèi)部接口
某軟件開(kāi)發(fā)項(xiàng)目,預(yù)算為40萬(wàn)元,計(jì)劃在40個(gè)工作日內(nèi)完成。當(dāng)項(xiàng)目進(jìn)行到第30個(gè)工作日時(shí),項(xiàng)目經(jīng)理對(duì)項(xiàng)目進(jìn)行了績(jī)效評(píng)估,結(jié)果是:項(xiàng)目完成當(dāng)期計(jì)劃進(jìn)度的70%,花費(fèi)23萬(wàn),按此績(jī)效還需投入( )萬(wàn)才能完成項(xiàng)目。
A、10
B、12
C、19
D、21
信息系統(tǒng)通過(guò)試運(yùn)行,系統(tǒng)的各種問(wèn)題都已經(jīng)暴露在用戶面前,這時(shí)通??梢钥紤]進(jìn)入()階段。
A.系統(tǒng)驗(yàn)收
B.系統(tǒng)維護(hù)
C.系統(tǒng)運(yùn)營(yíng)
D.系統(tǒng)試運(yùn)行
某待開(kāi)發(fā)的信息系統(tǒng)工作分解結(jié)構(gòu)圖如下圖,其中標(biāo)有“(1)”的方框應(yīng)該填入的內(nèi)容是()
A、同行評(píng)審
B、計(jì)劃評(píng)審
C、項(xiàng)目計(jì)劃制定
D、集成方案制定
TCP/IP協(xié)議是因特網(wǎng)的基礎(chǔ)協(xié)議,一般將其分成四層:數(shù)據(jù)鏈路層,網(wǎng)絡(luò)層。傳輸層和應(yīng)用層,( )屬于網(wǎng)絡(luò)層協(xié)議。
A、TCP
B、SNMP
C、ICMP
D、ARP
溫馨提示:因考試政策、內(nèi)容不斷變化與調(diào)整,信管網(wǎng)網(wǎng)站提供的以上信息僅供參考,如有異議,請(qǐng)以權(quán)威部門(mén)公布的內(nèi)容為準(zhǔn)!
信管網(wǎng)致力于為廣大信管從業(yè)人員、愛(ài)好者、大學(xué)生提供專(zhuān)業(yè)、高質(zhì)量的課程和服務(wù),解決其考試證書(shū)、技能提升和就業(yè)的需求。
信管網(wǎng)軟考課程由信管網(wǎng)依托10年專(zhuān)業(yè)軟考教研傾力打造,官方教材參編作者和資深講師坐鎮(zhèn),通過(guò)深研歷年考試出題規(guī)律與考試大綱,深挖核心知識(shí)與高頻考點(diǎn),為學(xué)員考試保駕護(hù)航。面授、直播&錄播,多種班型靈活學(xué)習(xí),滿足不同學(xué)員考證需求,降低課程學(xué)習(xí)難度,使學(xué)習(xí)效果事半功倍。
發(fā)表評(píng)論 查看完整評(píng)論 | |