系統(tǒng)集成項目管理工程師當天每日一練試題地址:www.jazzmuze.com/exam/ExamDay.aspx?t1=2
往期系統(tǒng)集成項目管理工程師每日一練試題匯總:www.jazzmuze.com/class/27/e2_1.html
系統(tǒng)集成項目管理工程師每日一練試題(2024/9/18)在線測試:www.jazzmuze.com/exam/ExamDay.aspx?t1=2&day=2024/9/18
系統(tǒng)集成項目管理工程師每日一練試題內(nèi)容(2024/9/18)
試題1
The project manager must maintain an effective communication link with the customer’s satisfaction with the progress of the project. The projectmanager maintains this link through( ).
A.Periodic project reports, periodic visits to the customer, and telephonic exchanges
B.Subordinates, project team members, and the project sponsor
C.One-time reports, weekly reports, and monthely reports
D.The telephone, facsimile, and data transmission
查看答案
試題參考答案:A
試題解析與討論:www.jazzmuze.com/exam/ExamDay.aspx?t1=2&day=2024/9/18
試題2
Categories of risk response are ( ).
A.Identification, quantification, response development, and response control
B.Marketing, technical, financial, and human
C.Avoidance, retention, control, and deflection
D.Avoidance, mitigation, acceptance, and Transferring
查看答案
試題參考答案:D
試題解析與討論:www.jazzmuze.com/exam/ExamDay.aspx?t1=2&day=2024/9/18
試題3
新型基礎設施主要包括信息基礎設施、融合基礎設施、創(chuàng)新基礎設施。其中,信息基礎設施凸顯“()”。查看答案
試題參考答案:B
試題解析與討論:www.jazzmuze.com/exam/ExamDay.aspx?t1=2&day=2024/9/18
試題4
The Purpose of ()is to ensure that the organization undertakes the right projects And Allocates critical resources Appropriately.查看答案
試題參考答案:A
試題解析與討論:www.jazzmuze.com/exam/ExamDay.aspx?t1=2&day=2024/9/18
試題5
Cloud computing is a style of computing in which dynamically scalabled often ( ) resources are provided as a service over the internet
A、 real
B、 rixed
C、 actual
D、 virtualized
查看答案
試題參考答案:D
試題解析與討論:www.jazzmuze.com/exam/ExamDay.aspx?t1=2&day=2024/9/18
試題6
招標人采用邀請招標方式的,應當向三個以上具備承擔招標項目的能力、資信良好的( )發(fā)出投標邀請書。
A.不特定的法人
B.特定的法人
C.不特定的法人或者其他組織
D.特定的法人或者其他組織
查看答案
試題參考答案:D
試題解析與討論:www.jazzmuze.com/exam/ExamDay.aspx?t1=2&day=2024/9/18
試題7
IEEE 802.3是()的協(xié)議。查看答案
試題參考答案:B
試題解析與討論:www.jazzmuze.com/exam/ExamDay.aspx?t1=2&day=2024/9/18
試題8
云計算中心提供的虛擬主機和存儲服務屬于( )。查看答案
試題參考答案:D
試題解析與討論:www.jazzmuze.com/exam/ExamDay.aspx?t1=2&day=2024/9/18
試題9
電子行業(yè)的標準代號是(),主管部門為()。
A.DJ,工業(yè)和信息化部
B.YD,工業(yè)和信息化部
C.DJ,人力資源和社會保障部
D.YD,人力資源和社會保障部
查看答案
試題參考答案:A
試題解析與討論:www.jazzmuze.com/exam/ExamDay.aspx?t1=2&day=2024/9/18
試題10
( )contributes to monitoring and data collection by defining security monitoring and date collection requirements.查看答案
試題參考答案:C
試題解析與討論:www.jazzmuze.com/exam/ExamDay.aspx?t1=2&day=2024/9/18
信管網(wǎng)訂閱號
信管網(wǎng)視頻號
信管網(wǎng)抖音號
溫馨提示:因考試政策、內(nèi)容不斷變化與調(diào)整,信管網(wǎng)網(wǎng)站提供的以上信息僅供參考,如有異議,請以權威部門公布的內(nèi)容為準!
信管網(wǎng)致力于為廣大信管從業(yè)人員、愛好者、大學生提供專業(yè)、高質(zhì)量的課程和服務,解決其考試證書、技能提升和就業(yè)的需求。
信管網(wǎng)軟考課程由信管網(wǎng)依托10年專業(yè)軟考教研傾力打造,教材和資料參編作者和資深講師坐鎮(zhèn),通過深研歷年考試出題規(guī)律與考試大綱,深挖核心知識與高頻考點,為學員考試保駕護航。面授、直播&錄播,多種班型靈活學習,滿足不同學員考證需求,降低課程學習難度,使學習效果事半功倍。
發(fā)表評論 查看完整評論 | |