PMP?每日一練試題內(nèi)容(2023/5/3)

  • 試題1

    在進(jìn)度匯報大會上項目經(jīng)理向大家匯報了項目的進(jìn)展。從目前的績效情況上來看,項目不是特別的樂觀。項目的初始預(yù)算為9.000w,目前為止實際花費為5,000w,計劃完成總工作的50%,而實際只完成了總工作的4 0%,通過分析,項目經(jīng)理發(fā)現(xiàn)此種典型績效會一直持續(xù)下去。高層希望知道按照此種績效的完工尚需估算是多少?還希望知道完工尚需績效指數(shù)是多少?如果項目經(jīng)理采用掙值技術(shù),他將怎樣按順序告訴高層這兩個答案?
    A、7.5kw,1.35
    B、7.5kw,0.72
    C、12.5kw,1.35
    D、12.5kw;0.72

    查看答案

    試題參考答案:A

    試題解析與討論:www.jazzmuze.com/st/4771612037.html

  • 試題2

    A project team identifies an emergency, which requires an immediate change. Due to the limited schedule.there is not enough time to follow a standard change control process. What should the project manager do next?
    項目團(tuán)隊識別到一個緊急事件,要求立即進(jìn)行變更。由于進(jìn)度計劃有限,沒有足夠的時間遵循標(biāo)準(zhǔn)的變更控制流程。項目經(jīng)理接下來應(yīng)該怎么做?
    A、Stop the project until the change is approved by the change control board 停止項目,直到變更獲得變更控制委員會的批準(zhǔn)為止
    B、Establish a new change control board to assess the change 建立新的變更控制委員會來評估變更
    C、Inform the project sponsor and ask for advice 通知項目發(fā)起人并詢問意見
    D、Document the change first and obtain approval from change control board at a later time
    首先記錄變更,并在之后獲得變更控制委員會的批準(zhǔn)

    查看答案

    試題參考答案:D

    試題解析與討論:www.jazzmuze.com/st/4766126688.html

  • 試題3

    A company's project management office(PMO)is responsible for coordinating projects in different countries. Some projects did not have financial success. What is one of the benefits a PMO brings to an organization ?
    某公司的項目管理辦公室(PMO)負(fù)責(zé)協(xié)調(diào)不同國家的項目。有些項目在財務(wù)上不成功。PMO給組織帶來的其中一個好處是什么?
    A、Provides adequate oversight of the company's project 為公司項目提供適當(dāng)?shù)谋O(jiān)督
    B、Provides oversight of successful projects 為成功項目提供監(jiān)督
    C、Keeps resources in successful projects 讓資源留在成功項目中
    D、Requires only reviews of unsuccessful projects on a regular basis 只需要定期審查不成功的項目

    查看答案

    試題參考答案:A

    試題解析與討論:www.jazzmuze.com/st/460286393.html

  • 試題4

    A client asks a global IT company to develop a supply chain monitoring system. A project manager then begins to assist i n the creation of the project charter for the project sponsor. What should the project manager do next?
    A. Search the lessons learned repository for historical inform action on project charter.
    B. Meet with key stakeholders and the sponsors to discuss project assumptions, success criteria, and critical inputs. C.Identify and define the most appropriate implementation approach for the project deliverables.
    D. Meet with the sponsors to outline a detailed timeline with project milestones for resource.
    客戶要求一家全球IT公司開發(fā)一個供應(yīng)鏈監(jiān)控系統(tǒng)。項目經(jīng)理隨后開始協(xié)助項目發(fā)起人制定項目章程。項目經(jīng)理下一步應(yīng)該怎么做?
    A、在經(jīng)驗教訓(xùn)知識庫中搜索制定項目章程的歷史信息。
    B、與關(guān)鍵相關(guān)方和發(fā)起人一起開會討論項目假設(shè)條件,成功標(biāo)準(zhǔn)和關(guān)鍵輸入。
    C、識別并定義項目可交付成果最適合的實施方法。
    D、為進(jìn)行資源分配,與發(fā)起人開會以概述出一個含有項目里程碑的詳細(xì)時間表。

    查看答案

    試題參考答案:B

    試題解析與討論:www.jazzmuze.com/st/4841114692.html

  • 試題5

    A project manager joins an ongoing project.At a weekly stat us meeting, the team informs the project manager that quality assurance will be carried out at the end of the project plan. What should a project manager do?
    A. Continue to implement the current quality assurance plan and ensure that the project is completed on time and on budget.
    B. Review quality assurance activities and update the project plan as each deliverable is completed.
    C.Use quality assurance to measure project team performance.
    D.Perform quality assurance periodically throughout the project's life cycle.
    一位項目經(jīng)理加入一個正在進(jìn)行的項目。在一次每周狀態(tài)會上,團(tuán)隊通知項目經(jīng)理,項目計劃中規(guī)定將在收尾階段執(zhí)行質(zhì)量保證。項目經(jīng)理應(yīng)該怎么做?
    A、繼續(xù)執(zhí)行當(dāng)期的質(zhì)量保證計劃,并確保項目按時、按預(yù)算完成
    B、重新審視質(zhì)量保證活動,并在完成每個可交付成果時更新項目計劃
    C、使用質(zhì)量保證來衡量項目團(tuán)隊績效
    D、在整個項目的生命周期中定期執(zhí)行質(zhì)量保證

    查看答案

    試題參考答案:D

    試題解析與討論:www.jazzmuze.com/st/4961322018.html

  • 試題6

    在項目執(zhí)行期間,公司被出售,相關(guān)方發(fā)生變化。一名新相關(guān)方詢問項目如何與公司的業(yè)務(wù)需求保持一致。項目經(jīng)理應(yīng)與相關(guān)方一起查閱下列哪份文件?
    A、項目管理計劃
    B、相關(guān)方參與計劃
    C、相關(guān)方登記冊
    D、需求文件

    查看答案

    試題參考答案:D

    試題解析與討論:www.jazzmuze.com/st/483419316.html

  • 試題7

    項目經(jīng)理需要具備多種能力才能讓項目成功。其中一個很重要的技能是戰(zhàn)略和商務(wù)管理技能。以下各項都屬于項目經(jīng)理需要具備的戰(zhàn)略和商務(wù)管理技能,除了∶
    A、向其他人解釋關(guān)于項目的必要商業(yè)信息
    B、針對每個項目裁剪傳統(tǒng)和敏捷工具、技術(shù)和方法
    C、與項目發(fā)起人、團(tuán)隊和主題專家合作制定合適的項目交付策略
    D、以實現(xiàn)項目商業(yè)價值最大化的方式執(zhí)行策略

    查看答案

    試題參考答案:B

    試題解析與討論:www.jazzmuze.com/st/4709027325.html

  • 試題8

    In the middle of a critical project, the project manager finds that the project is behind schedule Which activity should the project manager perform to bring the project back on track?
    在一個關(guān)鍵項目的中間階段,項目經(jīng)理發(fā)現(xiàn)項目落后于進(jìn)度。項目經(jīng)理應(yīng)該執(zhí)行下列哪一項活動將項目拉回到正常進(jìn)度軌道?
    A、Resource leveling 資源平衡
    B、Adjusting leads and lags 調(diào)整提前期量與滯后量
    C、Schedule compression 進(jìn)度壓縮
    D、What-if scenario analysis 假設(shè)場景分析

    查看答案

    試題參考答案:C

    試題解析與討論:www.jazzmuze.com/st/4938813718.html

  • 試題9

    為了節(jié)省一個項目的費用.公司管理層希望復(fù)制之前一個項目的需求.項目經(jīng)理應(yīng)使用什么工具或技術(shù)來制定項目需求?
    A、頭腦風(fēng)暴
    B、原型法
    C、標(biāo)桿對照
    D、文件分析

    查看答案

    試題參考答案:C

    試題解析與討論:www.jazzmuze.com/st/4646310240.html

  • 試題10

    The lessons learned are organizational process assets collected and document, which is following times?()
    經(jīng)驗教訓(xùn)屬于在下列哪一個時間點收集和記錄的組織過程資產(chǎn)?()
    A、During the last project assets update of document 在最后一次項目資產(chǎn)文件更新期間
    B、During a post-mortem meeting hosted by the project management office in the end the last week 在收尾階段最后一周由項目管理辦公室召開的事后分析會議期間
    C、Throughout the project life cycle 在整個項目生命周期
    D、In each time update the change request 在每次更新變更請求時

    查看答案

    試題參考答案:C

    試題解析與討論:www.jazzmuze.com/st/4602319722.html

信管網(wǎng)訂閱號

信管網(wǎng)視頻號

信管網(wǎng)抖音號

溫馨提示:因考試政策、內(nèi)容不斷變化與調(diào)整,信管網(wǎng)網(wǎng)站提供的以上信息僅供參考,如有異議,請以權(quán)威部門公布的內(nèi)容為準(zhǔn)!

信管網(wǎng)致力于為廣大信管從業(yè)人員、愛好者、大學(xué)生提供專業(yè)、高質(zhì)量的課程和服務(wù),解決其考試證書、技能提升和就業(yè)的需求。

信管網(wǎng)軟考課程由信管網(wǎng)依托10年專業(yè)軟考教研傾力打造,教材和資料參編作者和資深講師坐鎮(zhèn),通過深研歷年考試出題規(guī)律與考試大綱,深挖核心知識與高頻考點,為學(xué)員考試保駕護(hù)航。面授、直播&錄播,多種班型靈活學(xué)習(xí),滿足不同學(xué)員考證需求,降低課程學(xué)習(xí)難度,使學(xué)習(xí)效果事半功倍。

相關(guān)內(nèi)容

發(fā)表評論  查看完整評論  

報考條件查詢

推薦文章

精選

課程

提問

評論

收藏