PMP?每日一練試題內(nèi)容(2022/8/9)
試題1
A newly appointed project manager learns that stakeholders are concerned about identified project issues and risks. They are dissatisfied that for over a month no communications hay e been received. What should the new project manager do?新任命的項(xiàng)目經(jīng)理獲悉,相關(guān)方對(duì)已識(shí)別到的項(xiàng)目問題和風(fēng)險(xiǎn)非常擔(dān)心,他們對(duì)一個(gè)多月沒有收到任何溝通表示不滿。項(xiàng)目經(jīng)理應(yīng)該怎么做?查看答案
試題參考答案:D
試題2
項(xiàng)目中的兩個(gè)團(tuán)隊(duì)關(guān)于產(chǎn)品的設(shè)計(jì)有太多的不同意見,你希望把兩種設(shè)計(jì)的優(yōu)點(diǎn)吸收進(jìn)來,并且建立一種避免沖突、強(qiáng)調(diào)共性的環(huán)境。這種矛盾處理是∶查看答案
試題參考答案:A
試題3
管理質(zhì)量團(tuán)隊(duì)人成員通知項(xiàng)目經(jīng)理在可交付成果中發(fā)現(xiàn)了1 00個(gè)缺陷。因此,必須中止項(xiàng)目的后續(xù)工作。項(xiàng)目經(jīng)理接下來應(yīng)該怎么做?查看答案
試題參考答案:A
試題4
在項(xiàng)目開始時(shí),一名關(guān)鍵資源計(jì)劃退休,項(xiàng)目經(jīng)理應(yīng)該怎么做?查看答案
試題參考答案:D
試題5
A project is behind schedule and over budget.As a result of increased stakeholder pressure,the project team has been pl aced under serious duress. This causes a conflict between the quality and production managers,with each blaming the other for the delays and cost overruns. What should the project manager do?查看答案
試題參考答案:C
試題6
你是一家汽車制造公司的項(xiàng)目經(jīng)理。由于下暴雨,供貨商提供的機(jī)器備件不能及時(shí)送達(dá)。你已經(jīng)預(yù)計(jì)到該種風(fēng),險(xiǎn)并在規(guī)劃風(fēng)險(xiǎn)應(yīng)對(duì)過程中對(duì)此進(jìn)行了規(guī)劃。因此,根據(jù)你的風(fēng)險(xiǎn)應(yīng)對(duì)計(jì)劃,你開始使用1年前購入但尚未使用的機(jī)器備件。然而,這使你的項(xiàng)目受到新風(fēng)險(xiǎn)的影響∶1 年未用的機(jī)器備件可能會(huì)使次品率提高。該新風(fēng)險(xiǎn)被稱作∶查看答案
試題參考答案:C
試題7
已經(jīng)花掉的資金,無論其用途是否合理,都不能再挽回,這是:查看答案
試題參考答案:C
試題8
項(xiàng)目經(jīng)理研究報(bào)紙文章,以確定哪些團(tuán)體可能影響項(xiàng)目,項(xiàng)目經(jīng)理執(zhí)行的是哪一個(gè)過程?查看答案
試題參考答案:B
試題9
喬治將被派到項(xiàng)目上負(fù)責(zé)采購有關(guān)工作,他在以下哪個(gè)文件中可以找到有關(guān)他的角色和職責(zé)描述? ()查看答案
試題參考答案:A
試題10
A risk has emerged that has not been anticipated in the risk register. Which risk monitoring tool should the project manager use to handle the situation?查看答案
試題參考答案:A
信管網(wǎng)訂閱號(hào)
信管網(wǎng)視頻號(hào)
信管網(wǎng)抖音號(hào)
溫馨提示:因考試政策、內(nèi)容不斷變化與調(diào)整,信管網(wǎng)網(wǎng)站提供的以上信息僅供參考,如有異議,請(qǐng)以權(quán)威部門公布的內(nèi)容為準(zhǔn)!
信管網(wǎng)致力于為廣大信管從業(yè)人員、愛好者、大學(xué)生提供專業(yè)、高質(zhì)量的課程和服務(wù),解決其考試證書、技能提升和就業(yè)的需求。
信管網(wǎng)軟考課程由信管網(wǎng)依托10年專業(yè)軟考教研傾力打造,教材和資料參編作者和資深講師坐鎮(zhèn),通過深研歷年考試出題規(guī)律與考試大綱,深挖核心知識(shí)與高頻考點(diǎn),為學(xué)員考試保駕護(hù)航。面授、直播&錄播,多種班型靈活學(xué)習(xí),滿足不同學(xué)員考證需求,降低課程學(xué)習(xí)難度,使學(xué)習(xí)效果事半功倍。
發(fā)表評(píng)論 查看完整評(píng)論 | |