2010年下半年軟考高級(jí)信息系統(tǒng)項(xiàng)目管理師綜合知識(shí)真題答案與解析:
● Project schedule management is made up of six management processes including: activity definition, activity sequencing, ( 71) , and schedule control by order.
(71)A.a(chǎn)ctivity duration estimating, schedule developing, activity resource estimating
B .a(chǎn)ctivity resource estimating, activity duration estimating, schedule development
C.schedule developing, activity resource estimating, activity duration estimating
D.a(chǎn)ctivity resource estimating, schedule developing, activity duration estimating
信管網(wǎng)解析:
項(xiàng)目時(shí)間管理包括使項(xiàng)目按時(shí)完成所必需的管理過程。進(jìn)度安排的準(zhǔn)確程度可能比成本估計(jì)的準(zhǔn)確程度更重要??紤]進(jìn)度安排時(shí)要把人員的工作量與花費(fèi)的時(shí)間聯(lián)系起來,合理分配工作量,利用進(jìn)度安排的有效分析方法來嚴(yán)格監(jiān)視項(xiàng)目的進(jìn)展情況,以使得項(xiàng)目的進(jìn)度不致被拖延。
項(xiàng)目時(shí)間管理過程包括:活動(dòng)定義、活動(dòng)排序、活動(dòng)的資源估算、活動(dòng)歷史估算、制定進(jìn)度計(jì)劃及進(jìn)度控制六個(gè)步驟。
以上六個(gè)步驟具有先后順序,因此選擇“活動(dòng)的資源估算”activity resource estimating、“活動(dòng)歷史估算”activity duration estimating、制定進(jìn)度計(jì)劃schedule development,所以選B。
信管網(wǎng)參考答案:B
溫馨提示:因考試政策、內(nèi)容不斷變化與調(diào)整,信管網(wǎng)網(wǎng)站提供的以上信息僅供參考,如有異議,請(qǐng)以權(quán)威部門公布的內(nèi)容為準(zhǔn)!
信管網(wǎng)致力于為廣大信管從業(yè)人員、愛好者、大學(xué)生提供專業(yè)、高質(zhì)量的課程和服務(wù),解決其考試證書、技能提升和就業(yè)的需求。
信管網(wǎng)軟考課程由信管網(wǎng)依托10年專業(yè)軟考教研傾力打造,官方教材參編作者和資深講師坐鎮(zhèn),通過深研歷年考試出題規(guī)律與考試大綱,深挖核心知識(shí)與高頻考點(diǎn),為學(xué)員考試保駕護(hù)航。面授、直播&錄播,多種班型靈活學(xué)習(xí),滿足不同學(xué)員考證需求,降低課程學(xué)習(xí)難度,使學(xué)習(xí)效果事半功倍。
發(fā)表評(píng)論 查看完整評(píng)論 | |