1、 The project schedule is more than a document that lays out the activities over time to representthe time dimension of the project, it is a management tool to be used for decision making. As such , the schedule is used bythe roject management team to( ).
A.Measure, delay, record, distribute , analyze, and direct
B.Plan, schedule, monitor, control, report, and forecast
C.Promote, highlight, monitor, control, forecast, and report
D.Emphasize, visualize, analyze, conceptualize, report and record
信管網(wǎng)參考答案:B
項目進度表是項目管理的一種時間維度,比時間安排更為重要。因此,項目管理團隊使用該進度計劃來()。
A、 測量、延遲、記錄、分發(fā)、分析和指導(dǎo)
B、 計劃、計劃、監(jiān)控、控制、報告和預(yù)測
C、 推廣、突出、監(jiān)控、控制、預(yù)測和報告
D、 強調(diào)、形象化、分析、概念化、報告和記錄
查看解析:http://www.jazzmuze.com/st/1018.html
2、 Which of he following Project Scope Management peocesses involves subdividing the major project deliverables into smaller, more manageablecomponents( ).
A.Scope Planing
B.Scope Verification
C.Scope Change Control
D.Scope Definition
信管網(wǎng)參考答案:D
以下哪個項目范圍管理流程涉及將主要項目交付物細分為更小、更易管理的組件()。
A、 范圍規(guī)劃
B、 范圍驗證
C、 范圍變更控制
D、 范圍定義
溫馨提示:因考試政策、內(nèi)容不斷變化與調(diào)整,信管網(wǎng)網(wǎng)站提供的以上信息僅供參考,如有異議,請以權(quán)威部門公布的內(nèi)容為準!
信管網(wǎng)致力于為廣大信管從業(yè)人員、愛好者、大學(xué)生提供專業(yè)、高質(zhì)量的課程和服務(wù),解決其考試證書、技能提升和就業(yè)的需求。
信管網(wǎng)軟考課程由信管網(wǎng)依托10年專業(yè)軟考教研傾力打造,官方教材參編作者和資深講師坐鎮(zhèn),通過深研歷年考試出題規(guī)律與考試大綱,深挖核心知識與高頻考點,為學(xué)員考試保駕護航。面授、直播&錄播,多種班型靈活學(xué)習(xí),滿足不同學(xué)員考證需求,降低課程學(xué)習(xí)難度,使學(xué)習(xí)效果事半功倍。
發(fā)表評論 查看完整評論 | |