PMP?當天每日一練試題地址:www.jazzmuze.com/exam/ExamDay.aspx?t1=33
往期PMP?每日一練試題匯總:www.jazzmuze.com/class/27/e33_1.html
PMP?每日一練試題(2023/3/20)在線測試:www.jazzmuze.com/exam/ExamDay.aspx?t1=33&day=2023/3/20
點擊查看:更多PMP?習題與指導
PMP?每日一練試題內(nèi)容(2023/3/20)
試題1
After a recent company board meeting,stakeholders have changed their product vision and re-established project goals. What should the agile team lead do to communicate these changes to the team?查看答案
試題參考答案:D
試題2
一個進展順利的項目開始錯過一些交付日期,項目經(jīng)理確定,在制定項目進度計劃時,并未考慮到團隊成員的休假計劃,若要避免這個問題,在規(guī)劃項目時,項目經(jīng)理應該事先做什么?查看答案
試題參考答案:C
試題3
如果項目團隊工作的地點不在同一個物理位置上,被稱為是虛擬團隊或組織結(jié)構(gòu),這將給團隊的溝通帶來很大的困難,面對虛擬團隊,項目經(jīng)理應該:查看答案
試題參考答案:C
試題4
After reviewing team members' skill profiles, the project manager determines specific required skills are missing. What should the project manager do to address this situation?()查看答案
試題參考答案:A
試題5
A manufacturer is experiencing a large number of returned it ems due to production line errors and defects. The product manager suspects that the root causes may be training and/or p oor inventory purchasing and sorting processes.Which to should be utilized to determine the precise root causes of the production problems?查看答案
試題參考答案:D
試題6
A consulting firm was awarded a mega credit card processing system revamping project. Having failed to deliver the expected product within budget the last two mega projects.what approach should the consulting firm take in the initial stages of the project to avoid past failures?()查看答案
試題參考答案:C
試題7
During the project,a team member tells you that a major risk identified by the team has occurred.However.it is not as serious as previously thought.What is the FIRST thing you should do?查看答案
試題參考答案:C
試題8
After identifying all tasks to be carried out in the project, the project manager allocates the tasks to each team member based on their skills. The project manager refers to which of the following documents?查看答案
試題參考答案:C
試題9
To create a project schedule, a project manager estimates resource constraints. Pro1ect team members work various hours and follow different holidays. Different members are assigned to multiple projects. To better understand resource constraints and impacts to the project. what should the project manager do?()查看答案
試題參考答案:A
試題10
An approved project change will require dedicated resources from an IT department. The resource's manager is unavailable to provide approval,but the resource is needed immediately to ensure that the project stays on schedule. What should the project manager do?查看答案
試題參考答案:B
信管網(wǎng)訂閱號
信管網(wǎng)視頻號
信管網(wǎng)抖音號
溫馨提示:因考試政策、內(nèi)容不斷變化與調(diào)整,信管網(wǎng)網(wǎng)站提供的以上信息僅供參考,如有異議,請以權(quán)威部門公布的內(nèi)容為準!
信管網(wǎng)致力于為廣大信管從業(yè)人員、愛好者、大學生提供專業(yè)、高質(zhì)量的課程和服務,解決其考試證書、技能提升和就業(yè)的需求。
信管網(wǎng)軟考課程由信管網(wǎng)依托10年專業(yè)軟考教研傾力打造,教材和資料參編作者和資深講師坐鎮(zhèn),通過深研歷年考試出題規(guī)律與考試大綱,深挖核心知識與高頻考點,為學員考試保駕護航。面授、直播&錄播,多種班型靈活學習,滿足不同學員考證需求,降低課程學習難度,使學習效果事半功倍。
發(fā)表評論 查看完整評論 | |