PMP?每日一練試題(2023/2/18)

PMP?當(dāng)天每日一練試題地址:www.jazzmuze.com/exam/ExamDay.aspx?t1=33

往期PMP?每日一練試題匯總:www.jazzmuze.com/class/27/e33_1.html

PMP?每日一練試題(2023/2/18)在線測試:www.jazzmuze.com/exam/ExamDay.aspx?t1=33&day=2023/2/18

點(diǎn)擊查看:更多PMP?習(xí)題與指導(dǎo)

PMP?每日一練試題內(nèi)容(2023/2/18)

  • 試題1

    下列對商業(yè)價(jià)值的描述,哪一項(xiàng)不是正確的?
    A.從商業(yè)運(yùn)作中獲得的可量化凈效益 
    B.指特定項(xiàng)目的成果能夠?yàn)橄嚓P(guān)方帶來的效益 
    C.包括有形效益(如貨幣資產(chǎn)和股東權(quán)益)和無形效益(如:商譽(yù)和品牌認(rèn)知度) 
    D.進(jìn)行項(xiàng)目管理過程中可以獲得商業(yè)價(jià)值,但運(yùn)營項(xiàng)目不能創(chuàng)造商業(yè)價(jià)值

    查看答案

    試題參考答案:D

    試題解析與討論:www.jazzmuze.com/st/5269313920.html

  • 試題2

    Since the client was on leave,a project manager handed over the deliverables of a successfully completed project to the client's project manager. One month later,the accounts team informs the project manager that client approval was rejected and involves were unpaid What should the project manager h ave done to avoid this
    由于客戶休假,項(xiàng)目經(jīng)理將已完成項(xiàng)目的可交付成果移交給客戶方的項(xiàng)目經(jīng)理。一個(gè)月后.財(cái)務(wù)團(tuán)隊(duì)通知項(xiàng)目經(jīng)理. 客戶拒絕批準(zhǔn)且未按發(fā)票付款。若要避免這個(gè)問題項(xiàng)目經(jīng)理應(yīng)該事先做什么
    A、Obtained sign-off from the client's representative 獲得客戶代表的簽字。
    B、Ensured that the contract indicated a customer payment process確保合同中注明客戶付款流程。
    C、Ensured quality deliverables through the project 確保整個(gè)項(xiàng)目的可交付成果質(zhì)量。
    D、Escalated the client's unavailability to the sponsor 將客戶不在崗的問題升級上報(bào)給發(fā)起人。

    查看答案

    試題參考答案:A

    試題解析與討論:www.jazzmuze.com/st/4793911069.html

  • 試題3

    一個(gè)10萬美元預(yù)算的項(xiàng)目中,開發(fā)人員完成了50%的任務(wù)。在階段的狀態(tài)評審會(huì)上,項(xiàng)目經(jīng)理發(fā)現(xiàn)團(tuán)隊(duì)成員需要加班三周來完成該項(xiàng)目剩下的工作。該項(xiàng)目的掙值是多少萬美元?)
    A、7
    B、6.25
    C、5
    D、4

    查看答案

    試題參考答案:C

    試題解析與討論:www.jazzmuze.com/st/4892529621.html

  • 試題4

    培訓(xùn)具有以下全部特性,除了:
    A、培訓(xùn)包括旨在提高項(xiàng)目團(tuán)隊(duì)成員能力的全部活動(dòng) 
    B、培訓(xùn)可以是正式或非正式的。培訓(xùn)方式包括課堂培訓(xùn)、在線培訓(xùn)、計(jì)算機(jī)輔助培訓(xùn)、在崗培訓(xùn)(由其他項(xiàng)目團(tuán)隊(duì)成員提供)輔導(dǎo)及訓(xùn)練 
    C、如果項(xiàng)目團(tuán)隊(duì)成員缺乏必要的管理技能或技術(shù),項(xiàng)目將被認(rèn)為不具備組織實(shí)施的核心能力,應(yīng)該外包或取消 
    D、如果項(xiàng)目團(tuán)隊(duì)成員缺乏必要的管理或技術(shù)技能,可以把對這種技能的培養(yǎng)作為項(xiàng)目工作的一部分

    查看答案

    試題參考答案:C

    試題解析與討論:www.jazzmuze.com/st/4263319603.html

  • 試題5

    在愿景會(huì)上,項(xiàng)目愿景是被誰定義和展示的
    A.管理者
    B.項(xiàng)目經(jīng)理
    C.客戶
    D.項(xiàng)目團(tuán)隊(duì)

    查看答案

    試題參考答案:C

    試題解析與討論:www.jazzmuze.com/st/529521887.html

  • 試題6

    由于最近發(fā)生的公交車安全事故,你所在的公交車公司決定開展一次安全大檢查,了解所存在的各種安全隱患。你和你的團(tuán)隊(duì)已經(jīng)完成了對公交車的現(xiàn)場檢查,也完成了對相關(guān)人員的大規(guī)模調(diào)查?,F(xiàn)在你們應(yīng)該使用以下哪個(gè)工具對安全事故進(jìn)行潛在原因分析?()
    A、控制圖
    B、影響圖
    C、因果圖
    D、流程圖

    查看答案

    試題參考答案:C

    試題解析與討論:www.jazzmuze.com/st/497433940.html

  • 試題7

    團(tuán)隊(duì)評價(jià)績效指標(biāo)不包括:
    A、個(gè)人技能的提升
    B、團(tuán)隊(duì)能力的提升 
    C、團(tuán)隊(duì)成員離職率降低 
    D、客戶滿意度的提高

    查看答案

    試題參考答案:D

    試題解析與討論:www.jazzmuze.com/st/426201499.html

  • 試題8

    Due to a lack of stakeholder support.a project manager with an approval project and budget is unable to certain resources. What should the project manager do?
    由于缺乏相關(guān)方的支持雖然項(xiàng)目和預(yù)算均已獲得批準(zhǔn),但項(xiàng)目經(jīng)理無法獲得資源。項(xiàng)目經(jīng)理應(yīng)該做什么?
    A、Escalate the issue to upper management. 將問題升級上報(bào)給上級管理層。
    B、Perform a stakeholder analysis,and hold a kick-off meeting to engage stakeholders. 執(zhí)行相關(guān)方分析,并舉行開工會(huì)議,讓相關(guān)方參與其中。
    C、Demand better stakeholder support at the next status meeting. 在下一次項(xiàng)目狀態(tài)會(huì)議上要求相關(guān)方提供更好的支持。
    D、Add the issue and the mitigation plan to the risk log,and notify the sponsor.Escalate the issue to upper management. 將問題和減輕計(jì)劃添加到風(fēng)險(xiǎn)日志中,并通知發(fā)起人。

    查看答案

    試題參考答案:B

    試題解析與討論:www.jazzmuze.com/st/4800214912.html

  • 試題9

    You have taken over a project from another manager who left the firm. This is a functional organization and the different units are often rather hostile to each other.The project is a large one involving activities that the organization has never d one before.You find that the project has what appears to be adequate documentation, including an agreed-to project chart er,project management plan, WBS, etc, The project is on schedule and within budget. However, the atmosphere in meetings with the project members often seems tense, and offhand comments made by participant seem to indicate a high level of dissatisfaction with the project. You review all of the major project documents with the key stakeholders and get agreement that they are still accurate, but this does not seem to solve the problem. What is the MOST likely explanation for this situation?()
    由于另外一位項(xiàng)目經(jīng)理離職,你接手了他的項(xiàng)目。你所在的公司是一個(gè)職能型的組織,不同部門之間互相充滿敵意。你負(fù)責(zé)的這個(gè)項(xiàng)目是一個(gè)大型的項(xiàng)目,項(xiàng)目活動(dòng)均是公司之前沒有接觸過的。你發(fā)現(xiàn)項(xiàng)目文件還是比較齊全,包括項(xiàng)目章程、項(xiàng)目管理計(jì)劃和工作分解結(jié)構(gòu)等等。項(xiàng)目進(jìn)度和預(yù)算均在計(jì)劃內(nèi)。然而,團(tuán)隊(duì)會(huì)議上的氣氛總是很緊張,與會(huì)者即興的發(fā)言充分表明他們對項(xiàng)目非常不滿。你和主要相關(guān)方評估了所有的主要項(xiàng)目文件,大家一致認(rèn)為這些文件都還是很準(zhǔn)確的,但這種舉措似乎沒有解決實(shí)際問題。出現(xiàn)此種問題的最佳原因應(yīng)該為∶()
    A、There are personality conflicts among the project tea m members that you need to uncover and resolve. 團(tuán)隊(duì)成員之間存在個(gè)性沖突,需要你來發(fā)現(xiàn)并給予解決。
    B、The project does not have an effective sponsor and thus is not viewed as a high priority. 此項(xiàng)目沒有一個(gè)有效的發(fā)起人,所以沒有較高的優(yōu)先級。
    C、Stakeholders have very different expectations about w hat the project is supposed to accomplish. 相關(guān)方對項(xiàng)目的完成結(jié)果存在不同的期望。
    D、The organizational structure and dynamics prevent people from working together effectively.公司的組織結(jié)構(gòu)及動(dòng)因防礙了團(tuán)隊(duì)成員之間有效的協(xié)作。

    查看答案

    試題參考答案:D

    試題解析與討論:www.jazzmuze.com/st/4603523253.html

  • 試題10

    在項(xiàng)目計(jì)劃階段,有8個(gè)項(xiàng)目相關(guān)方被識(shí)別;項(xiàng)目執(zhí)行過程中,又發(fā)現(xiàn)原來遺漏掉的2個(gè)重要相關(guān)方。此時(shí),項(xiàng)目潛在的溝通渠道增加了多少?
    A、28 
    B、17
    C、16
    D、45 

    查看答案

    試題參考答案:B

    試題解析與討論:www.jazzmuze.com/st/49275666.html

信管網(wǎng)訂閱號(hào)

信管網(wǎng)視頻號(hào)

信管網(wǎng)抖音號(hào)

溫馨提示:因考試政策、內(nèi)容不斷變化與調(diào)整,信管網(wǎng)網(wǎng)站提供的以上信息僅供參考,如有異議,請以權(quán)威部門公布的內(nèi)容為準(zhǔn)!

信管網(wǎng)致力于為廣大信管從業(yè)人員、愛好者、大學(xué)生提供專業(yè)、高質(zhì)量的課程和服務(wù),解決其考試證書、技能提升和就業(yè)的需求。

信管網(wǎng)軟考課程由信管網(wǎng)依托10年專業(yè)軟考教研傾力打造,教材和資料參編作者和資深講師坐鎮(zhèn),通過深研歷年考試出題規(guī)律與考試大綱,深挖核心知識(shí)與高頻考點(diǎn),為學(xué)員考試保駕護(hù)航。面授、直播&錄播,多種班型靈活學(xué)習(xí),滿足不同學(xué)員考證需求,降低課程學(xué)習(xí)難度,使學(xué)習(xí)效果事半功倍。

相關(guān)內(nèi)容

發(fā)表評論  查看完整評論  

報(bào)考條件查詢

推薦文章

精選

課程

提問

評論

收藏