A project manager learns that a team member changed a customer requirement to provide higher value and that work to implement this change has already started. What should the project manager do?
項(xiàng)目經(jīng)理了解到,一名團(tuán)隊(duì)成員變更客戶需求以提供更高價(jià)值,而且實(shí)施這一變更的工作已經(jīng)開始,項(xiàng)目經(jīng)理應(yīng)該怎么做?
A.Escalate the issue to the project sponsor.將該問題上報(bào)給項(xiàng)目發(fā)起人
B.Direct the team member to immediately revise their work to meet the customer’s original requirement.指示該團(tuán)隊(duì)成員立即修改工作,滿足客戶的原始需要
C.Instruct the team member to stop working on the change until receipt of change control board (CCB)approval.指示該團(tuán)隊(duì)成員停止變更的工作,直到收到變更控制委員會(huì)(CCB)的批準(zhǔn)
D.Approve the change and document it in the change log.批準(zhǔn)該變更,并將其記錄在變更日志中
信管網(wǎng)參考答案:C
信管網(wǎng)解析:
C是參考答案。有價(jià)值的變更不應(yīng)該直接否定,應(yīng)該遵循變更控制流程。參考章節(jié)4.6實(shí)施整體變更控制。
信管網(wǎng)訂閱號(hào)
信管網(wǎng)視頻號(hào)
信管網(wǎng)抖音號(hào)
溫馨提示:因考試政策、內(nèi)容不斷變化與調(diào)整,信管網(wǎng)網(wǎng)站提供的以上信息僅供參考,如有異議,請(qǐng)以權(quán)威部門公布的內(nèi)容為準(zhǔn)!
信管網(wǎng)致力于為廣大信管從業(yè)人員、愛好者、大學(xué)生提供專業(yè)、高質(zhì)量的課程和服務(wù),解決其考試證書、技能提升和就業(yè)的需求。
信管網(wǎng)軟考課程由信管網(wǎng)依托10年專業(yè)軟考教研傾力打造,教材和資料參編作者和資深講師坐鎮(zhèn),通過深研歷年考試出題規(guī)律與考試大綱,深挖核心知識(shí)與高頻考點(diǎn),為學(xué)員考試保駕護(hù)航。面授、直播&錄播,多種班型靈活學(xué)習(xí),滿足不同學(xué)員考證需求,降低課程學(xué)習(xí)難度,使學(xué)習(xí)效果事半功倍。
在項(xiàng)目的制造階段,在工程圖紙中發(fā)現(xiàn)一個(gè)錯(cuò)誤,該錯(cuò)誤
在一個(gè)項(xiàng)目中途,項(xiàng)目團(tuán)隊(duì)意識(shí)到他們低估了交付一部分
A project manager discov
IT團(tuán)隊(duì)之前發(fā)送了有關(guān)如何訪問項(xiàng)目溝通所采用的新工
項(xiàng)目經(jīng)理在收尾一個(gè)項(xiàng)目時(shí)遇到問題,因?yàn)橄嚓P(guān)方不接受
由于超出項(xiàng)目經(jīng)理控制的原因,項(xiàng)目落后于進(jìn)度,一名有
在項(xiàng)目執(zhí)行期間,由于行業(yè)趨勢(shì)下行和產(chǎn)品價(jià)格下降,客
在測(cè)試期間,一位團(tuán)隊(duì)成員將某個(gè)質(zhì)量缺陷升級(jí)上報(bào)給項(xiàng)
在新項(xiàng)目啟動(dòng)會(huì)議期間,因?yàn)轫?xiàng)目將需要采購(gòu)新設(shè)備,生
技術(shù)進(jìn)步創(chuàng)造了一項(xiàng)組織需求,需要改善一個(gè)產(chǎn)品線的規(guī)
發(fā)表評(píng)論 查看完整評(píng)論 | |