  • 試題1

    (  )is the process of obtaining the stakeholders' formal acceptance of the completed project scope. Verifying the scope includes reviewing deliverables and work results to ensure that all were completed satisfactorily.
    A. Project acceptance
    B. Scope verification
    C. Scope definition
    D. WBS Creation

    查看答案

    試題參考答案:B

    試題解析與討論:www.jazzmuze.com/exam/ExamDay.aspx?t1=1&day=2024/7/22

  • 試題2

    假設甲、乙二人合作開發(fā)了某應用軟件,甲為主要開發(fā)者。該應用軟件所得收益合理分配后,甲自行將該軟件作為自己獨立完成的軟件作品發(fā)表,甲的行為( )。
    A. 不構成對乙權利的侵害
    B. 構成對乙權利的侵害
    C. 已不涉及乙的權利
    D. 沒有影響乙的權利

    查看答案

    試題參考答案:B

    試題解析與討論:www.jazzmuze.com/exam/ExamDay.aspx?t1=1&day=2024/7/22

  • 試題3

    項目經理向客戶推薦了四種供應商選擇方案。每個方案損益值已標在下面的決策樹上。根據預期收益值,應選擇設備供應商( )。

    A.1
    B.2
    C.3
    D.4

    查看答案

    試題參考答案:A

    試題解析與討論:www.jazzmuze.com/exam/ExamDay.aspx?t1=1&day=2024/7/22

  • 試題4

    乙公司中標承接了甲機構的網絡工程集成項目,在合同中約定了因不可抗力因素導致工期延誤免責的條款,其中不會被甲機構認可的不可抗力因素是(1),合同約定,甲乙雙方一旦出現分歧,在協商不成時,可提交到相關機構裁定,一般優(yōu)先選擇的裁定機構是(2)
    (1)A、施工現場遭遇長時間雷雨天氣
    B、物流公司車輛遭遇車禍
    C、乙方施工隊領導遭遇意外情況
    D、施工現場長時間停電
    (2)A、甲機構所在地的仲裁委員會
    B、乙公司所在地的仲裁委員會
    C、甲機構所在地的人民法院
    D、乙公司所在地的人民法院

    查看答案

    試題參考答案:C、A

    試題解析與討論:www.jazzmuze.com/exam/ExamDay.aspx?t1=1&day=2024/7/22

  • 試題5

    某電池廠生產甲、乙兩種型號產品(單位:萬個),這兩種產品都需要設備和A、B兩種原材料,利潤與資源限制條件如表所示,為了獲得最大的利潤,該電池廠每天生產的甲產品的數量應為( 1 )萬個,此時該企業(yè)每天的利潤為( 2 )萬元。

    (1) A
    A、1
    B、2
    C、3
    D、4
    (2)D
    A、20
    B、22
    C、24
    D、26

    查看答案

    試題參考答案:A、D

    試題解析與討論:www.jazzmuze.com/exam/ExamDay.aspx?t1=1&day=2024/7/22

  • 試題6

    At the project establishment stage , the feasibility study mainly includes techinical feasibility analysis , (), operation environment feasibility analysis and other aspects of feasibility analysis.
    A.detail feasibility analysis
    B.opportunity analysis
    C.economic feasibility analysis
    D.risk analysis

    查看答案

    試題參考答案:C

    試題解析與討論:www.jazzmuze.com/exam/ExamDay.aspx?t1=1&day=2024/7/22

  • 試題7

    以下工程進度網絡圖中,若結點0和6 分別表示起點和終點,則關鍵路徑為( )。

    A.0→1→3→6
    B.0→1→4→6
    C.0→1→2→4→6
    D.0→2→5→6

    查看答案

    試題參考答案:C

    試題解析與討論:www.jazzmuze.com/exam/ExamDay.aspx?t1=1&day=2024/7/22

  • 試題8

    The receiving  activities conduct analyses of the requirements with the requirements provider to ensure that a compatible, shared understandin  is reached on the meaning of the requirements. The result of this analysis and dialog is an ( )set of requirements.
    A. agreed-to
    B. agree-to
    C. agree-to-do
    D. agree-with

    查看答案

    試題參考答案:A

    試題解析與討論:www.jazzmuze.com/exam/ExamDay.aspx?t1=1&day=2024/7/22

  • 試題9

    有8口海上油井,相互間距離如下表所示(單位:海里)。其中1號井離海岸最短長度,為5海里,先要從海岸經1號井鋪設油管將各井連接起來,則鋪設輸油管道的最短長度()海里。

    A、9.1
    B、9.2
    C、10.1
    D、10.2

    查看答案

    試題參考答案:D

    試題解析與討論:www.jazzmuze.com/exam/ExamDay.aspx?t1=1&day=2024/7/22

  • 試題10

    根據合同法的相關條款,下面敘述,( )是錯誤的。
    A、合同解除后,己經履行的,根據履行情況和合同性質,當事人可以要求恢復原狀、采取其他補救措施,并有權要求賠償損失
    B、當事人互負到期債務,該債務的標的物種類、品質相同的,一般情況下任何一方可以將自己的債務與對方的債務抵銷
    C、當事人互負債務,標的物種類、品質不相同的,均不可以抵銷
    D、當事人采用信件、數據電文等形式訂立合同的,可以在合同成立之前要求簽訂確認書

    查看答案

    試題參考答案:C

    試題解析與討論:www.jazzmuze.com/exam/ExamDay.aspx?t1=1&day=2024/7/22

信管網訂閱號

信管網視頻號

信管網抖音號

溫馨提示:因考試政策、內容不斷變化與調整,信管網網站提供的以上信息僅供參考,如有異議,請以權威部門公布的內容為準!

信管網致力于為廣大信管從業(yè)人員、愛好者、大學生提供專業(yè)、高質量的課程和服務,解決其考試證書、技能提升和就業(yè)的需求。

信管網軟考課程由信管網依托10年專業(yè)軟考教研傾力打造,教材和資料參編作者和資深講師坐鎮(zhèn),通過深研歷年考試出題規(guī)律與考試大綱,深挖核心知識與高頻考點,為學員考試保駕護航。面授、直播&錄播,多種班型靈活學習,滿足不同學員考證需求,降低課程學習難度,使學習效果事半功倍。

相關內容

發(fā)表評論  查看完整評論  

推薦文章

精選

課程

提問

評論

收藏