系統(tǒng)集成項(xiàng)目管理工程師每日一練試題內(nèi)容(2024/7/14)
試題1
下表給出了某信息化建設(shè)項(xiàng)目到2019年8月1日為止的成本執(zhí)行(績(jī)效)數(shù)據(jù),如果當(dāng)前的成本偏差是非典型的,則完工估算(EAC)為()元。查看答案
試題參考答案:B
試題解析與討論:www.jazzmuze.com/exam/ExamDay.aspx?t1=2&day=2024/7/14
試題2
The ETL technology is mainly used in ( ) stage.查看答案
試題參考答案:A
試題解析與討論:www.jazzmuze.com/exam/ExamDay.aspx?t1=2&day=2024/7/14
試題3
下列選項(xiàng)中不屬于招標(biāo)階段監(jiān)理服務(wù)基礎(chǔ)活動(dòng)的是()。查看答案
試題參考答案:D
試題解析與討論:www.jazzmuze.com/exam/ExamDay.aspx?t1=2&day=2024/7/14
試題4
執(zhí)行過(guò)程組的主要目標(biāo)是()查看答案
試題參考答案:C
試題解析與討論:www.jazzmuze.com/exam/ExamDay.aspx?t1=2&day=2024/7/14
試題5
關(guān)于估算成本和制定預(yù)算的描述,不正確的是:()。查看答案
試題參考答案:A
試題解析與討論:www.jazzmuze.com/exam/ExamDay.aspx?t1=2&day=2024/7/14
試題6
依據(jù)下面的項(xiàng)目活動(dòng)網(wǎng)絡(luò)圖中,該項(xiàng)目歷時(shí)為( )天。
A. 10
B. 11
C. 13
D. 18
查看答案
試題參考答案:D
試題解析與討論:www.jazzmuze.com/exam/ExamDay.aspx?t1=2&day=2024/7/14
試題7
The () plan is aiming to integrate the Internet with traditional industries, and fuel economic growth.
A、Internet Plus action
B、Internet action
C、Web Plus action
D、Net Plus action
查看答案
試題參考答案:A
試題解析與討論:www.jazzmuze.com/exam/ExamDay.aspx?t1=2&day=2024/7/14
試題8
( )is a method used in Critical Path Methodology for constructing a project schedule network diagram that uses boxes or rectangles, referred to as nodes, to represent activities and connects them with arrows that show the logical relationships that exist between them.
A.PERT
B.AOA
C.WBS
D.PDM
查看答案
試題參考答案:D
試題解析與討論:www.jazzmuze.com/exam/ExamDay.aspx?t1=2&day=2024/7/14
試題9
信息系統(tǒng)文檔的管理主要體現(xiàn)在文檔書寫規(guī)范、圖表編號(hào)規(guī)則、文檔目錄編寫標(biāo)準(zhǔn)和( )等幾個(gè)方面。
A.文檔管理方法
B.文檔管理制度
C.建立文檔規(guī)范
D.文檔使用權(quán)限控制
查看答案
試題參考答案:B
試題解析與討論:www.jazzmuze.com/exam/ExamDay.aspx?t1=2&day=2024/7/14
試題10
individual project risk is an uncertain event or condition that, if it occurs, has a ( )effect on one or more project objectives.查看答案
試題參考答案:A
試題解析與討論:www.jazzmuze.com/exam/ExamDay.aspx?t1=2&day=2024/7/14
信管網(wǎng)訂閱號(hào)
信管網(wǎng)視頻號(hào)
信管網(wǎng)抖音號(hào)
溫馨提示:因考試政策、內(nèi)容不斷變化與調(diào)整,信管網(wǎng)網(wǎng)站提供的以上信息僅供參考,如有異議,請(qǐng)以權(quán)威部門公布的內(nèi)容為準(zhǔn)!
信管網(wǎng)致力于為廣大信管從業(yè)人員、愛(ài)好者、大學(xué)生提供專業(yè)、高質(zhì)量的課程和服務(wù),解決其考試證書、技能提升和就業(yè)的需求。
信管網(wǎng)軟考課程由信管網(wǎng)依托10年專業(yè)軟考教研傾力打造,教材和資料參編作者和資深講師坐鎮(zhèn),通過(guò)深研歷年考試出題規(guī)律與考試大綱,深挖核心知識(shí)與高頻考點(diǎn),為學(xué)員考試保駕護(hù)航。面授、直播&錄播,多種班型靈活學(xué)習(xí),滿足不同學(xué)員考證需求,降低課程學(xué)習(xí)難度,使學(xué)習(xí)效果事半功倍。
發(fā)表評(píng)論 查看完整評(píng)論 | |