系統(tǒng)集成項目管理工程師每日一練試題內(nèi)容(2024/4/23)
試題1
“十四五”規(guī)劃和2035遠景目標綱要就打造()新優(yōu)勢、加快()建設,提高()建設水平,營造良好(),做出成績。查看答案
試題參考答案:A
試題解析與討論:www.jazzmuze.com/exam/ExamDay.aspx?t1=2&day=2024/4/23
試題2
( )is a method used in Critical Path Methodology for constructing a project schedule network diagram that uses boxes or rectangles, referred to as nodes, to represent activities and connects them with arrows that show the logical relationships that exist between them.
A.PERT
B.AOA
C.WBS
D.PDM
查看答案
試題參考答案:D
試題解析與討論:www.jazzmuze.com/exam/ExamDay.aspx?t1=2&day=2024/4/23
試題3
SWOT analysis is a kind of risk identification method. If the project team chose the SO strategy, they should ( ).
A.make full use of the advantage and catch the opportunity
B.overcome the weakness and catch the opportunity
C.make full use of the advantage and reduce the threat
D.overcome the weakness and reduce the threat
查看答案
試題參考答案:A
試題解析與討論:www.jazzmuze.com/exam/ExamDay.aspx?t1=2&day=2024/4/23
試題4
下表給出某信息化建設項目到2017年9月1日為止的成本執(zhí)行(績效)數(shù)據(jù),基于該數(shù)據(jù),項目經(jīng)理對完工估算(EAC)進行預測,假設當前的成本偏差被看作是可代表未來偏差的典型偏差時,EAC應為()元。
A、45000.00
B、50000.00
C、53200.00
D、62500.00
查看答案
試題參考答案:D
試題解析與討論:www.jazzmuze.com/exam/ExamDay.aspx?t1=2&day=2024/4/23
試題5
The project life-cycle can be described as( ).
A.project concept, project planning, project execution, and project close-out
B.project planning, work authorization, and project reporting
C.project planning, project control, project definition, WBS development, and project termination
D.project concept, project execution, and project reporting
查看答案
試題參考答案:A
試題解析與討論:www.jazzmuze.com/exam/ExamDay.aspx?t1=2&day=2024/4/23
試題6
下表給出了某信息化建設項目到2019年8月1日為止的成本執(zhí)行(績效)數(shù)據(jù),如果當前的成本偏差是非典型的,則完工估算(EAC)為()元。查看答案
試題參考答案:B
試題解析與討論:www.jazzmuze.com/exam/ExamDay.aspx?t1=2&day=2024/4/23
試題7
在某單位招標過程中發(fā)生了如下事件,根據(jù)中華人民共和國招投標法及其實施條例,當出現(xiàn)( )之一時,評標委員會應當否決其投標。
①投標文件未經(jīng)投標單位蓋章和單位負責人簽字
②同一投標人提交兩個以上不同的投標文件,但招標文件未要求提交備選投標
③投標報價高于招標文件設定的最高投標價
④投標書中包括投標聯(lián)合體共同簽發(fā)的報價折扣聲明
A、①②
B、①②④
C、①③④
D、①②③
查看答案
試題參考答案:D
試題解析與討論:www.jazzmuze.com/exam/ExamDay.aspx?t1=2&day=2024/4/23
試題8
( )is the process of identifying individual project risks as well as source of overall project risk, and documenting their characteristics.查看答案
試題參考答案:A
試題解析與討論:www.jazzmuze.com/exam/ExamDay.aspx?t1=2&day=2024/4/23
試題9
軟件文檔管理指南GB/T 16680--1996將文檔的質(zhì)量按文檔的形式和列出要求劃分為四級,分別是最底限度文檔,內(nèi)部文檔,( )和正式文檔
A、外部文檔
B、管理文檔
C、工作文檔
D、臨時文檔
查看答案
試題參考答案:C
試題解析與討論:www.jazzmuze.com/exam/ExamDay.aspx?t1=2&day=2024/4/23
試題10
New information technology includes ()查看答案
試題參考答案:D
試題解析與討論:www.jazzmuze.com/exam/ExamDay.aspx?t1=2&day=2024/4/23
信管網(wǎng)訂閱號
信管網(wǎng)視頻號
信管網(wǎng)抖音號
溫馨提示:因考試政策、內(nèi)容不斷變化與調(diào)整,信管網(wǎng)網(wǎng)站提供的以上信息僅供參考,如有異議,請以權威部門公布的內(nèi)容為準!
信管網(wǎng)致力于為廣大信管從業(yè)人員、愛好者、大學生提供專業(yè)、高質(zhì)量的課程和服務,解決其考試證書、技能提升和就業(yè)的需求。
信管網(wǎng)軟考課程由信管網(wǎng)依托10年專業(yè)軟考教研傾力打造,教材和資料參編作者和資深講師坐鎮(zhèn),通過深研歷年考試出題規(guī)律與考試大綱,深挖核心知識與高頻考點,為學員考試保駕護航。面授、直播&錄播,多種班型靈活學習,滿足不同學員考證需求,降低課程學習難度,使學習效果事半功倍。
發(fā)表評論 查看完整評論 | |