試題1
The project has been going relatively well,although there have been some problems with resource availability and the project scope has changed more than was expected. The project is now completing one of its phase.Of all decisions the sponsor must consider during an end-of-phase review meeting,the MOST difficult is:查看答案
試題參考答案:C
試題2
A customer has given you a contract statement of work for a complex, eight month project that has a few unknowns. The customer has asked you to just"get it done" and only wants t o see you at the end of eight months when you deliver the finished project.Under these circumstances, which of the following is the BEST thing to do?查看答案
試題參考答案:A
試題3
以下都是識(shí)別相關(guān)的,除了:查看答案
試題參考答案:D
試題4
有一個(gè)敏捷團(tuán)隊(duì)成員,他既是一名領(lǐng)域?qū)<?,也是一個(gè)產(chǎn)品的用戶代理。在交付測(cè)試產(chǎn)品后,客戶報(bào)告了多個(gè)產(chǎn)品問題。下列哪個(gè)角色應(yīng)該指為用戶代理查看答案
試題參考答案:A
試題5
The project is close to completion.All project deliverable ha ye been accepted by the stakeholders. The program manager has asked the project manager to take on another project.All external contracts have been met and all the contracts closed. What should the project manager do?查看答案
試題參考答案:C
試題6
During project discussions with key stakeholders.a few stake holder express their disagreement on the project's potential benefits.How should the project manager facilitate the meeting?查看答案
試題參考答案:B
試題7
在項(xiàng)目中途兩名團(tuán)隊(duì)成員辭職這對(duì)原來計(jì)劃的工作量造成不利影響下一份項(xiàng)目報(bào)告將顯示什么內(nèi)容?查看答案
試題參考答案:C
試題8
During the initiating stage,a project manager realizes that main milestones are misaligned with the scope,which may cause misinterpretation. What should the project manager do next?查看答案
試題參考答案:A
試題9
在項(xiàng)目執(zhí)行階段結(jié)束時(shí),一名關(guān)鍵相關(guān)方識(shí)別到一個(gè)可能影響項(xiàng)目交付日期的風(fēng)險(xiǎn),項(xiàng)目經(jīng)理應(yīng)該怎么做?查看答案
試題參考答案:C
試題10
A government-approved taxation change must be implement ed in six months,what should the project manager do查看答案
試題參考答案:C
信管網(wǎng)訂閱號(hào)
信管網(wǎng)視頻號(hào)
信管網(wǎng)抖音號(hào)
溫馨提示:因考試政策、內(nèi)容不斷變化與調(diào)整,信管網(wǎng)網(wǎng)站提供的以上信息僅供參考,如有異議,請(qǐng)以權(quán)威部門公布的內(nèi)容為準(zhǔn)!
信管網(wǎng)致力于為廣大信管從業(yè)人員、愛好者、大學(xué)生提供專業(yè)、高質(zhì)量的課程和服務(wù),解決其考試證書、技能提升和就業(yè)的需求。
信管網(wǎng)軟考課程由信管網(wǎng)依托10年專業(yè)軟考教研傾力打造,教材和資料參編作者和資深講師坐鎮(zhèn),通過深研歷年考試出題規(guī)律與考試大綱,深挖核心知識(shí)與高頻考點(diǎn),為學(xué)員考試保駕護(hù)航。面授、直播&錄播,多種班型靈活學(xué)習(xí),滿足不同學(xué)員考證需求,降低課程學(xué)習(xí)難度,使學(xué)習(xí)效果事半功倍。
發(fā)表評(píng)論 查看完整評(píng)論 | |
关于我们 ┊ 付款方式 ┊ 联系我们 ┊ 加入我们 ┊ 网站声明 ┊ QQ学习群 ┊ 网站地图 ┊ 最近更新 |
客服热线:400-880-6318 QQ:800184589 微信:270019001 文章或图片如有侵权,请第一时间联系删除 |
Copyright ©2010-2022 信息化项目管理专业网站 - 信管网 All Rights Reserved 湘ICP备15005302号-9 湘公网安备 43010402000418号 |
![]() |
预约信管网直播
信管网视频号
信管网抖音号
无特殊情况一般晚上8点直播
很高兴能和大家一路同行
下面是我的微信和抖音号,一起加油!
直播时间:晚上8点
12年+
专业培训机构
PMI®注册
教育机构
10年+
专业教研团队
无忧保障,不
过免费重学