PMP?每日一練試題內(nèi)容(2022/9/27)
試題1
敏捷團隊希望使用累計流量圖與干系人溝通可預(yù)測的交付,若要有效的利用這個圖標(biāo),他們需要什么數(shù)據(jù)?查看答案
試題參考答案:D
試題2
There is a potential delay in the internal manufacturing of materials. It is decided that part of the materials will be bought from a third-party manufacturer. What should the project manager work on next?查看答案
試題參考答案:B
試題3
敏捷項目團隊決定采用使用中的才是過程。這一決定在那一次會議上產(chǎn)生的?查看答案
試題參考答案:A
試題4
項目的啟動階段,項目經(jīng)理得知相關(guān)方可能以多種消極和積極的方式影響項目。項目經(jīng)理應(yīng)該∶查看答案
試題參考答案:B
試題5
項目經(jīng)理與項目相關(guān)方開會.獲得關(guān)于如何最好地向施工現(xiàn)場輸送用品的信息和知識,這使用的是哪種溝通方法類型?查看答案
試題參考答案:A
試題6
All feature of the product are completed.A developer suggests the addition of a new feature. The project manager should do which of the following?查看答案
試題參考答案:A
試題7
在一次經(jīng)驗教訓(xùn)會議中,項目經(jīng)理應(yīng)該記錄哪項信息用于持續(xù)改進?查看答案
試題參考答案:C
試題8
A project manager determines that the a project's schedule performance index(SPD)is 1.2,and its cost performance index(CPI)is 0.8.What is the project a current status查看答案
試題參考答案:D
試題9
項目經(jīng)理資源有限,無法獲得更多資源,項目經(jīng)理應(yīng)該使用什么技術(shù)來充分利用現(xiàn)有資源,而不會令項目完成時間延期?查看答案
試題參考答案:A
試題10
一個項目需要采取預(yù)防措施以滿足安全需求,以避免在審計時采取糾正措施。然后,一個相關(guān)方不認同項目的成功標(biāo)準(zhǔn)。項目經(jīng)理應(yīng)如何在收尾報告中收集績效?查看答案
試題參考答案:A
信管網(wǎng)訂閱號
信管網(wǎng)視頻號
信管網(wǎng)抖音號
溫馨提示:因考試政策、內(nèi)容不斷變化與調(diào)整,信管網(wǎng)網(wǎng)站提供的以上信息僅供參考,如有異議,請以權(quán)威部門公布的內(nèi)容為準(zhǔn)!
信管網(wǎng)致力于為廣大信管從業(yè)人員、愛好者、大學(xué)生提供專業(yè)、高質(zhì)量的課程和服務(wù),解決其考試證書、技能提升和就業(yè)的需求。
信管網(wǎng)軟考課程由信管網(wǎng)依托10年專業(yè)軟考教研傾力打造,教材和資料參編作者和資深講師坐鎮(zhèn),通過深研歷年考試出題規(guī)律與考試大綱,深挖核心知識與高頻考點,為學(xué)員考試保駕護航。面授、直播&錄播,多種班型靈活學(xué)習(xí),滿足不同學(xué)員考證需求,降低課程學(xué)習(xí)難度,使學(xué)習(xí)效果事半功倍。
發(fā)表評論 查看完整評論 | |